FIR08-00605
| INSP-Sprinkler Rough-in | 1/2/2009 | 1/5/2009 | 1/6/2009 6:19:31 PM | P | DEFR |
|
|
tony Note: to cover Phone #: ###-####
|
BLD08-01845
| FIRE-Final Inspection | 1/5/2009 | 1/5/2009 | 1/5/2009 3:49:42 PM | P | PASS |
|
|
Life safety passed inspection.
|
BLD06-02303
| FIRE-Conference | 1/5/2009 | 1/5/2009 | 1/5/2009 3:48:55 PM | P | DONE |
|
|
Regarding project scheduling for permit finals.
|
FIR08-00812
| INSP-Final Inspection | 1/2/2009 | 1/5/2009 | 1/5/2009 12:51:34 PM | P | PART |
|
|
Scope of work inspected and approved however, noted one obstructed head at the NE corner of the computer/server room to be adjusted for correct coverage prior to this permit final. See plans for annotated location with today's date.
|
FIR08-00670
| INSP-Final Inspection | 1/2/2009 | 1/5/2009 | 1/5/2009 12:46:42 PM | A | PART |
|
|
Work appears to have been completed, however vestibule framing is not finished and therefore min. separation between heads is not provided at this time.
|
BLD08-01034
| FIRE-Final Inspection | 12/31/2008 | 1/5/2009 | 1/5/2009 11:48:50 AM | A | FAIL |
|
|
Project related fire alarm permit is not yet finaled, discussed EM lighting and certification for the PFE's.
|