Inspections for the day of: Wednesday, January 5, 2011.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR10-00443 FIR-Aging Inspection1/5/20111/5/20111/12/2011 2:01:22 PM NR
work is in progress per trent
FIR09-00510 FIR-Aging Inspection1/5/20111/5/20111/12/2011 1:59:08 PM NR
Matt is waiting on a change order for this project.
FIR09-00638 FIR-Aging Inspection1/5/20111/5/20111/12/2011 1:46:37 PM NR
I left a message on Charlie's voice mail requesting project status.
FIR09-00321 INSP-Final Inspection1/5/20111/5/20111/6/2011 1:10:29 PMPPASS
Permit finaled
FIR10-00107 INSP-Final Inspection1/5/20111/5/20111/5/2011 3:41:05 PMPFAIL
All signals tested okay except there was no access to inspector's test switch to verify water flow switch activation. Provide 7.5ah battery.
FIR10-00108 INSP-Final Inspection1/5/20111/5/20111/5/2011 3:39:14 PMPFAIL
Call permit desk with the correct address (19 not 15). Provide as-builts and provide a 7.5 ah battery for the AES panel.
FIR10-00613 INSP-Sprinkler Rough-in1/5/20111/5/20111/5/2011 3:36:59 PMPPASS
Sprinkler piping is okay to cover.
BLD10-00987 FIRE-Conference1/5/20111/5/20111/5/2011 3:31:54 PMPDONE
Signs directing the fire dept to the fire alarm panel location in the construction area were not being maintained. I spoke to the job superintendant and he posted a new sign.
BLD10-02366 FIRE-Final Inspection1/5/20111/5/20111/5/2011 3:27:49 PMPPASS
Life safety passed
BLD10-02736 FIRE-Final Inspection1/4/20111/5/20111/5/2011 10:56:49 AMAPASS
life safety passed