Inspections for the day of: Thursday, January 5, 2012.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR03-00052 FIR-Aging Inspection1/5/20121/5/20121/11/2012 11:28:43 AM DONE
No contractor scheduled inspections for seven years and I have been unable to contact the contractor for the last two years. Permit is being DOC finaled.
BLD11-02954 FIRE-Conference1/4/20121/5/20121/5/2012 3:56:46 PMAPASS
Matt and I went over life safety requirements.
BLD11-01490 FIRE-Final Inspection1/4/20121/5/20121/5/2012 11:37:50 AMAPASS
life safety passed
FIR11-00632 INSP-Final Inspection1/5/20121/5/20121/5/2012 11:37:20 AMPPASS
permit finaled
FIR11-00543 INSP-Sprinkler Rough-in1/4/20121/5/20121/5/2012 11:26:16 AMAPART
Area "B" was inspected today. The general installation is ok but the 4" main routing has been changed by the addition of four elbows. Plans need to be resubmitted with revised hydraulic calculations due to the remote area only having a 5% cushion. The earth quake bracing is not complete on the 4" main. No cover in area "B" until I can verify the E.Q. bracing.
BLD11-01767 FIRE-Final Inspection1/4/20121/5/20121/5/2012 11:14:43 AMAPASS
life safety passed
FIR11-00631 INSP-Sprinkler Rough-in1/4/20121/5/20121/5/2012 9:57:19 AMAPASS
Rough-in passed. Office area piping is not yet complete. Also still need the hydro tests and air test of the dry system.