FIR17-00768
| INSP-Sprinkler Rough-in/Hydro | 1/4/2018 | 1/5/2018 | 1/5/2018 11:25:13 AM | A | PASS |
|
|
The overhead rough-in and hydro test passed for the new addition. Contractor will add the branchline restraints before next inspection as discussed.
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
FIR17-00593
| INSP-Sprinkler Rough-in | 1/5/2018 | 1/5/2018 | 1/5/2018 11:06:09 AM | A | PASS |
|
|
Rough-in passed
|
FIR17-00631
| INSP-Sprinkler Rough-in | 1/5/2018 | 1/5/2018 | 1/5/2018 11:05:09 AM | A | PASS |
|
|
Rough-in passed. Correctlons have been made at the mezzanine
|
FIR17-00687
| INSP-Sprinkler Rough-in | 1/5/2018 | 1/5/2018 | 1/5/2018 11:04:21 AM | A | PASS |
|
|
Rough-in passed.
|
FIR17-00772
| INSP-Sprinkler Rough-in | 1/4/2018 | 1/5/2018 | 1/5/2018 11:03:32 AM | A | PART |
|
|
Rough-in is ok but plans need to be resubmitted showing the change out of all the existing pendant heads to new pendant heads.
|
FIR17-00320
| INSP-Final Inspection | 1/4/2018 | 1/5/2018 | 1/5/2018 9:17:40 AM | A | PASS |
|
|
Permit finaled
|
BLD16-04310
| FIRE-Final Inspection | 1/4/2018 | 1/5/2018 | 1/5/2018 9:14:54 AM | A | PASS |
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by David Scaggs
|
FIR17-00499
| INSP-Sprinkler Rough-in | 1/4/2018 | 1/5/2018 | 1/5/2018 9:03:50 AM | A | PART |
|
|
Sprinkler piping in Rooms 200 and 208 is ok to cover but the pendant head in the Electrical Closet is overspaced.
cecil Phone #: ###-####
|