MEC98-03999
| INSP - Final | 1/6/1999 | 1/6/1999 | 1/6/1999 12:00:00 AM | P | FAIL |
|
|
took for wes...no access, left tag.
|
MEC98-03999
| INSP - Final | 1/6/1999 | 1/6/1999 | 1/6/1999 12:00:00 AM | P | FAIL |
|
|
took for wes...no access, left tag.
|
MEC98-04470
| INSP - Framing/ Rough-in | 1/6/1999 | 1/6/1999 | 1/6/1999 12:00:00 AM | P | PASS |
|
|
p/t & r/i ok
|
BLD98-02505
| INSP - Foundation | 1/6/1999 | 1/6/1999 | 1/6/1999 12:00:00 AM | P | PART |
|
|
Albertsons at 36th & State...conf w/ supt...they have begun special insp log. All soils compaction, concrete, and masonry req spec. insp. WIP for excavation.
|
BLD98-02690
| INSP - Framing/Rough-in | 1/6/1999 | 1/6/1999 | 1/6/1999 12:00:00 AM | P | PART |
|
|
wood thru penetrations removed from 1hr wall; still need to nail off all 1hr gypsum; to be done by drywallers per Jack Barber. will reinspect. ok to begin cover...plbg vents moved> 5' from commn wall at roof.
|
BLD98-02693
| INSP - Framing/Rough-in | 1/6/1999 | 1/6/1999 | 1/6/1999 12:00:00 AM | P | FAIL |
|
|
reinsp...c/n, need to complete drywall install at 1hr wall, install beam hanger, laminate beam, repair overbored studs & corner cut out for plbg at hse/gar wall. fireblocks, etc. move vents> 5'from common wall at roof.
|