Inspections for the day of: Friday, January 6, 2006.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD05-02735 FIRE-Conference1/6/20061/6/20061/6/2006 5:13:49 PMPDONE
Went over life safety notes with contractor
BLD05-01459 FIRE-Conference1/6/20061/6/20061/6/2006 3:51:37 PMPDONE
Had conference on curbing painting. No area needs painting.
FIR05-00571 INSP-Sprinkler Rough-in/Hydro1/6/20061/6/20061/6/2006 3:20:46 PMPPART
Need to finish sprinkler expansion into the existing areas of the church. Per the structural inspector wall in two rooms will need to be extended to the deck. This may effect sprinkler coverage. I can find no record of a hydro test which will need to be done before the permit is finaled. Forward flush of the backflow preventor passed.
BLD05-01215 FIRE-Conference1/6/20061/6/20061/6/2006 3:17:22 PMPPASS
Fire life safety finaled
BLD04-02937 FIRE-Final Inspection1/5/20061/6/20061/6/2006 3:16:36 PMAFAIL
Need signage or painting of the curb when the final happens. Knox key box and occupant load signs need installed for the new addition. Per Dave Hanneman a temp is ok when fire alarm and fire sprinkler is complete in the new addition.
FIR05-00590 FIR-Aging Inspection1/6/20061/6/20061/6/2006 2:05:31 PM NR
Contractor is waiting for an informational letter on the generator to give to Mary.
FIR05-00664 INSP-Final Inspection1/5/20061/6/20061/6/2006 1:31:12 PMPFAIL
Alarm system was not ready to test. I did a walk through and found one location in the basement where the spot detector for the fire/smoke damper activation exceeded 5' from the damper. They are going to relocate it.
FIR05-00773 INSP-Final Inspection1/5/20061/6/20061/6/2006 10:45:09 AMAPASS
Permit finaled