ESC09-00352
| Conference | 1/5/2010 | 1/7/2010 | 1/7/2010 3:22:25 PM | A | DONE |
|
|
11:00 a.m. Reviewed overall areas of the project. I informed the group of the importance of thinking about stabilizing the areas that are not being worked. It was stated that the entire area is being worked and then It was recommended to the contractor that the SWPPP inspection reports must be able to justify that the areas are still active. Also reviewed the intake area and it was stressed to all that turbid water and other pollutants cannot be discharged into the river and that stabilization must be completed upon completion of the project.
|