FIR14-00018
| INSP-Sprinkler Rough-in | 1/7/2014 | 1/7/2014 | 1/7/2014 3:39:25 PM | P | CANC |
|
|
Cancel per troy Phone #: ###-####
|
FIR13-00709
| INSP-Sprinkler Rough-in | 1/7/2014 | 1/7/2014 | 1/7/2014 3:15:29 PM | P | PASS |
|
|
Rough-in passed. Piping can not be covered until a tenting inspection has been performed.
|
FIR13-00697
| INSP-Sprinkler Rough-in | 1/7/2014 | 1/7/2014 | 1/7/2014 2:53:39 PM | P | PASS |
|
|
Todays inspection was to verify earth quake clamp, top beam clamp and retaining strap installation prior to the spray on fire proofing. It looked good.
|
FIR13-00681
| INSP-Sprinkler Rough-in | 1/6/2014 | 1/7/2014 | 1/7/2014 2:51:51 PM | A | PASS |
|
|
See areas marked "ok" on plans where piping is ok to cover.
|
BLD13-02724
| FIRE-Final Inspection | 1/6/2014 | 1/7/2014 | 1/7/2014 9:23:21 AM | A | PASS |
|
|
life safety passed
|
BLD13-01876
| FIRE-Final Inspection | 1/6/2014 | 1/7/2014 | 1/7/2014 9:21:47 AM | A | PASS |
|
|
life safety passed
|