Inspections for the day of: Thursday, January 7, 2016.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRex Boyles
TitleELE-INSPECTOR
Phone #685-9023
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE13-00256 ELE-Aging Inspection1/7/20161/7/20161/7/2016 1:47:49 PM DONE
mailbox full could'nt leave message
ELE15-03943 Final1/7/20161/7/20161/7/2016 1:16:45 PMPNR
We are requesting a final inspection for this afternoon. Our contact is Luke @ ###-####. Thank you Phone #: ###-#### Inspection requested via web by Clint Tate not ready still hardwiring office furniture, arc flash stickers still neededon loadcenters
ELE15-03849 Electrical Rough-In1/7/20161/7/20161/7/2016 12:12:12 PMAPASS
We would like an inspection for cover on our underground, we will need to uncover the slab site first thing in the morning, If possible could you come by after 10 in the morning to make sure its uncovered for you. Phone #: ###-#### Inspection requested via web by Stan Woodward r/i underslab raceways and floorboxes ok to cover
ELE15-00495 Conference1/6/20161/7/20161/7/2016 12:10:59 PMADONE
Would like to go over fire pump feeds and options on site again. Would like to discuss 695.4(B)(3) interpretation. Contact is Toby Groves. ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves discuss disconnect locations for fire pump utility power and generator power. OK to install disconnects inside Telco Demarc room if painted red and satisfying all other items in 695. Also maintain access and 2 hr protection to pullboxes or condulets if installed.
ELE13-01291 Electrical Rough-In1/6/20161/7/20161/7/2016 11:31:43 AMAPASS
Call Brandon to inspect all JUMP elect. rooms levels 1,2,3,4,5,6 for completness. Phone #: ###-#### Inspection requested via web by Tom Betty Final ok on all electrical rooms. Still need final inspections on unfinished party decks and marketplace areas, Slide electrical and Pioneer Path electrical not completed, all electric signs "by others" and parking control pedestal electrical wiring "by others" before "FINAL" inspection on whole Jump project.