BLD01-01477
| BLD-Conference | 1/5/2004 | 1/6/2003 | | A | |
|
|
donna ###-#### -call 1st before insp
|
MIS02-00244
| MIS-Aging Inspection | 1/8/2003 | 1/8/2003 | 1/8/2003 12:00:00 AM | | DONE |
|
|
|
BLD02-01618
| BLD-Final | 1/7/2003 | 1/8/2003 | 1/8/2003 12:00:00 AM | A | FAIL |
|
|
call gayle first ###-####
need to complete demising wall per plan, trade sign off, final letter of satisfaction on epoxy bolting, c/n posted 1/8/2003 9:52:40 AM
|
MEC03-00046
| Rough-in | 1/7/2003 | 1/8/2003 | 1/8/2003 12:00:00 AM | A | DONE |
|
|
###-####
|
MEC03-00046
| Pressure Test | 1/7/2003 | 1/8/2003 | 1/8/2003 12:00:00 AM | A | DONE |
|
|
|
MEC02-03830
| Pressure Test | 1/7/2003 | 1/8/2003 | 1/8/2003 12:00:00 AM | A | DONE |
|
|
Scheduled by a contractor via Hello! on 01/07/2003 at 18:09:56. Contact: ###-####.
|
BLD02-02906
| BLD-Energy code compliance | 1/8/2003 | 1/8/2003 | 1/8/2003 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 01/08/2003 at 07:53:18. Contact: ###-####.
|
BLD02-02866
| BLD-Framing/Rough-in | 1/8/2003 | 1/8/2003 | 1/8/2003 12:00:00 AM | P | FAIL |
|
|
###-####
c/n posted, ok to insulate 1/8/2003 4:13:28 PM
|
MEC02-03830
| Pressure Test | 1/8/2003 | 1/8/2003 | 1/8/2003 12:00:00 AM | P | PASS |
|
|
|
MEC02-03047
| Final | 1/8/2003 | 1/8/2003 | 1/8/2003 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 01/08/2003 at 10:56:30. Contact: ###-####.no access 1/8/2003 2:25:45 PM
|
MEC02-03120
| Final | 1/8/2003 | 1/8/2003 | 1/8/2003 12:00:00 AM | P | FAIL |
|
|
###-#### no access 1/8/2003 2:23:17 PM
|
BLD02-02395
| BLD-Conference | 12/27/2002 | 1/8/2003 | 1/8/2003 12:00:00 AM | P | NH |
|
|
415 to recheck
|