Inspections for the day of: Thursday, January 8, 2009.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC06-00899 Site Final1/8/20091/8/20091/8/2009 4:03:06 PMPPASS
ESC08-00412 General Inspection1/8/20091/8/20091/8/2009 3:17:52 PM PASS
ESC08-00411 General Inspection1/8/20091/8/20091/8/2009 3:12:43 PM PASS
ESC08-01022 Tracking Control1/8/20091/8/20091/8/2009 2:05:06 PMPFAIL
Verbal Notice to RP.
1. Clean up all sediment and debris from all hard surfaces.
2. Install a sediment barrier at slope of disturbance along Five Mile.
Will re-inspect on 1/09/09.
ESC08-00784 BMP Violation1/8/20091/8/20091/8/2009 10:57:56 AMAFAIL
Need to clean up all hard surface of sediment and debris. Re-install bmp's at the east side of the driveway. Will re-inspect 1/9/09
ESC08-00737 Tracking Control1/7/20091/8/20091/8/2009 10:33:14 AMAFAIL
Talk with RP and also the dirt workers.
Prior to any storm event or end of the day to clean all hard surface of all sediment and debris. Will re-inspect 1/9/09.
ESC08-00577 General Inspection1/8/20091/8/20091/8/2009 10:10:37 AM PASS
ESC08-00924 BMP Violation1/7/20091/8/20091/8/2009 9:48:12 AMAPART
Correction Notice has been lifted. Went over with Rocky (Public Work PM) and Bob (Somer Const. Foreman/ Operater) over areas and issues of concern.
1. Inspect on a daily basis the perimeter of the basin (berm) for any over flow or boils. Correct as needed.
2. Inspect the Jersey Barrier dam for complete closure when water is turbid, so no discharging is reaching the wetland area of Wallings Creek.
3. When discharging turbid water into basin to inspect ALL discharge point of of the basin into the wetland area periododically.
Will re-inspect on a daily basis.
ESC08-00924 BMP Violation1/7/20091/8/20091/8/2009 9:32:13 AMACANC
Duplicate.
ESC08-00924 General Inspection1/5/20091/8/20091/7/2009 10:37:40 AMAFAIL
(Left message with the RP)
Correction Notice:
1. Discharging of turbid water into the watland area. Not into the sedling basin.
2. Devert all tubid water into the basin ara by block ing off the wetland discharge point by the use of the deversion Dam.
Fail ure to comply will result in a stop work order.