Inspections for the day of: Friday, January 8, 2010.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC09-00507 General Inspection1/7/20101/8/20101/8/2010 2:12:09 PMPPASS
ESC09-00719 Site Final1/7/20101/8/20101/8/2010 1:52:04 PMPFAIL
Temporary BMP's still in place.
ESC09-00736 Tracking Control1/7/20101/8/20101/8/2010 1:12:01 PMPPASS
ESC09-00511 Tracking Control1/8/20101/8/20101/8/2010 9:38:01 AMAFAIL
Message to RP:
CLean up tracking off of the south end of project area. Will re-inspect on 1/11/09
ESC09-00510 Tracking Control1/8/20101/8/20101/8/2010 9:37:52 AMAFAIL
Message to RP:
CLean up tracking off of the south end of project area. Will re-inspect on 1/11/09
ESC09-00509 Tracking Control1/8/20101/8/20101/8/2010 9:37:40 AMAFAIL
Message to RP:
CLean up tracking off of the south end of project area. Will re-inspect on 1/11/09
ESC09-00508 Tracking Control1/8/20101/8/20101/8/2010 9:37:27 AMAFAIL
Message to RP:
CLean up tracking off of the south end of project area. Will re-inspect on 1/11/09
ESC09-00201 Tracking Control1/7/20101/8/20101/8/2010 9:22:36 AMAPART
Verbal to RP:
Still cleaning up tracking. Need to maintain the the construction exit on the west end of project.
ESC09-00770 Tracking Control1/7/20101/8/20101/8/2010 9:21:21 AMAPART
ESC09-00769 Tracking Control1/7/20101/8/20101/8/2010 9:19:35 AMAPART
ESC09-00805 Site Preparation1/4/20101/8/20101/8/2010 9:04:33 AMANR
ESC09-00386 General Inspection1/6/20101/8/20101/7/2010 11:19:01 AMAPASS
payment(check with Tisha)