Inspections for the day of: Friday, January 8, 2016.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR15-00551 INSP-Supply line flush1/8/20161/8/20161/8/2016 3:07:08 PMPPASS
Underground flush passed
BLD15-04267 FIRE-Conference1/8/20161/8/20161/8/2016 2:36:00 PMPDONE
John and I spoke about general life safety requirements.
FIR15-00769 INSP-Sprinkler Rough-in1/7/20161/8/20161/8/2016 1:07:51 PMAPASS
see the city approved plans for piping abobe hard lib is ok for cover.
BLD15-04453 FIRE-Final Inspection1/7/20161/8/20161/8/2016 10:59:07 AMAPASS
Life safety passed
FIR15-00794 INSP-Final Inspection1/7/20161/8/20161/8/2016 10:53:59 AMAPART
Todays inspection was just to verify that the visual devices sync'd in phase one which they did.
BLD15-04455 FIRE-Final Inspection1/7/20161/8/20161/8/2016 9:22:41 AMAPASS
life safety passed
BLD15-04127 FIRE-Final Inspection1/7/20161/8/20161/8/2016 8:55:47 AMAPASS
Life safety passed. I spoke to plan review and Carl was ok with this being used as a storage area. I spoke to lee and fire alarm notification will not be required.