ELE20-00087 Electrical Rough-In1/8/20201/8/20201/8/2020 3:01:49 PMPPASS
Rough in cover of walls. Phone #: ###-#### Inspection requested via web by Steve Craig Ok cover walls and grd work for 2 floor box location.
ELE19-04815 Final1/8/20201/8/20201/8/2020 2:03:31 PMPPASS
Call office or Albert (###-####) if there are any questions. Phone #: ###-#### Inspection requested via web by Bryan Atkins Ok final
ELE19-04903 Electrical Rough-In1/7/20201/8/20201/8/2020 1:46:31 PMPPASS
Please contact Bryce (Foreman) @ ###-#### or Barry (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes Ok cover. Items UL listed
ELE20-00063 Final1/7/20201/8/20201/8/2020 1:03:14 PMPPASS
Phone #: ###-#### Inspection requested via web by Dan Hilke Ok final. Tankless has GFI protection, 15a max circuit to new furnace.
ELE19-04001 Final1/8/20201/8/20201/8/2020 12:34:51 PMPPASS
Please give me a call a half an hour before inspection to insure access. Thank you Shaun ###-#### Phone #: ###-#### Inspection requested via web by Shaun Kirkman Ok final mstr bath.
ELE19-03060 Final1/8/20201/8/20201/8/2020 12:34:29 PMPPASS
Contact: Jason Konrad Phone #: ###-#### Inspection requested via web by Deb Gooden Ok final. Tested pool cover and lights when I did grd work inspection for front gates and pool. Panel was also labeled.
ELE19-00664 Electrical Rough-In1/8/20201/8/20201/8/2020 12:06:59 PMPPASS
Floor heat Phone #: ###-#### Inspection requested via web by Jim Williams Ok cover floor heat mstr
ELE20-00079 Electrical Rough-In1/7/20201/8/20201/8/2020 10:22:52 AMAPASS
Inspection requested via web by shane miller Ok cover up bath. New sub panel in basement
ELE20-00066 Final1/7/20201/8/20201/8/2020 10:18:04 AMAPASS
Inspection requested via web by Dan Hobdey Ok final. GFI functions properly
ELE19-04395 Final1/7/20201/8/20201/8/2020 10:17:32 AMAPASS
Inspection requested via web by Dan Hobdey Ok final. Corrections made.
ELE19-04739 Final1/6/20201/8/20201/8/2020 9:28:38 AMAPASS
Approved Plans on site in solar disconnect. All work was performed to approved plans, no deviation necessary. If you have any questions please call Josh at 208.731.0577 Phone #: ###-#### Inspection requested via web by Bryan Lawley Ok final. Line side connection
ELE19-00947 Electrical Rough-In1/7/20201/8/20201/8/2020 8:55:13 AMAPASS
Andy Phone #: ###-#### Ok cover 1st floor ceiling flex room, and 2nd floor ceilings hall and 2 bathrooms
ELE20-00063 Final1/6/20201/8/20201/7/2020 9:37:20 PMACANC
Two dedicated 15A 120V circuits from main panel outside to new furnace and tankless water heater located in basement. Call Wyatt for details. Thanks. Phone #: ###-#### >> Inspection requested via web by Dan Hilke Inspection cancelled from web by: Dan Hilke