Inspections for the day of: Wednesday, January 9, 2008.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00473 INSP-Final Inspection1/9/20081/9/20081/10/2008 10:08:30 AMPPASS
Fire alarm permit finaled.
FIR07-00885 INSP-Final Inspection1/8/20081/9/20081/9/2008 4:37:32 PMPPASS
Fire sprinkler permit finaled.
FIR07-00888 INSP-Final Inspection1/9/20081/9/20081/9/2008 3:22:26 PMPPASS
Fire sprinkler permit finaled.
BLD06-03529 FIRE-Final Inspection1/8/20081/9/20081/9/2008 3:20:51 PMAPART
Final pending shell and core permit finals.
FIR07-00473 INSP-Alarm Testing1/9/20081/9/20081/9/2008 3:20:08 PMAPASS
Fire alarm work passed field testing,
BLD07-01778 FIRE-Final Inspection1/8/20081/9/20081/9/2008 12:30:16 PMPNR
Project is not ready for final inspection, pending application of IFC 2003 sec. 1008.1.3.4.
BLD07-02244 FIRE-Final Inspection1/8/20081/9/20081/9/2008 12:26:10 PMAPASS
Fire life safety inspection completed satisfactory.
BLD06-01188 FIRE-Final Inspection1/8/20081/9/20081/9/2008 12:25:15 PMAPART
3rd floor fire life safety is satisfactory, noted the posted fire extinguishers are currently in process of re-certification to be completed promptly as discussed.
FIR06-00595 INSP-Alarm Testing1/8/20081/9/20081/9/2008 12:22:01 PMAPART
Fire alarm testing for the 3rd floor SW quad passed.
FIR07-00976 INSP-Supply line flush1/8/20081/9/20081/9/2008 12:21:05 PMAFAIL
No water supply available to complete flushing as required.
FIR07-00710 FIR-Aging Inspection1/9/20081/9/20081/9/2008 10:20:49 AM DEFR
Construction underway, wip.
FIR07-00737 INSP-Final Inspection1/8/20081/9/20081/9/2008 10:19:03 AMANR
Need project related fire alarm permit work inspection.
FIR07-00913 INSP-Final Inspection1/8/20081/9/20081/9/2008 10:17:38 AMANR
Pending related alarm work for system supervision.
FIR07-00606 INSP-Sprinkler Rough-in1/8/20081/9/20081/9/2008 10:14:13 AMAPART
Verified seismic restraint attatchments for beam clamps installed at the locker room areas on the east side of the building prior to fireproofing.
FIR07-00974 INSP-Conference1/9/20081/9/20081/9/2008 10:11:37 AMADONE
Regarding site inspection schedule.
FIR07-00888 INSP-Final Inspection1/8/20081/9/20081/9/2008 9:28:48 AMPCANC
final inspection Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley