ESC13-00082
| General Inspection | 1/9/2014 | 1/9/2014 | 1/9/2014 5:50:42 PM | | CANC |
|
|
Unable to inspect due to illness. No issues during recent inspections.
|
ESC13-01202
| Site Preparation | 1/9/2014 | 1/9/2014 | 1/9/2014 1:36:20 PM | P | PART |
|
|
Site is ready, but need to clearly post ESC permit sign and details.
|
ESC13-00230
| Random Inspection | 1/9/2014 | 1/9/2014 | 1/9/2014 1:17:43 PM | P | FAIL |
|
|
West side of central area needs silt fence protection and possibly a sediment basin. Snow melt runoff running into street and stormwater infrastructure. No new signage observed. No payment of previously issued re-inspection fee.
Called Brighton SWPPP contact Daniel Frisbee to request corrections as soon as conditions allow. Pictures of event are on file.
|
ESC13-00475
| General Inspection | 1/9/2014 | 1/9/2014 | 1/9/2014 12:18:03 PM | | PASS |
|
|
Not yet landscaped or stabilized, but majority of house appears complete. Contractors are parking on street instead of muddy driveway. No trackout or other violations observed.
|
ESC13-01041
| General Inspection | 1/9/2014 | 1/9/2014 | 1/9/2014 9:57:31 AM | | PASS |
|
|
Paving project and new loading dock construction is not yet complete. No violations observed. Permit is posted. No MS4 or surface waters in vicinity.
|
ESC13-00502
| Aging Inspection | 1/9/2014 | 1/9/2014 | 1/9/2014 9:44:50 AM | | PASS |
|
|
House is mostly complete. No activity. Appears to be stabilized and landscaped - will check next inspection when no snow cover.
|
ESC13-00425
| General Inspection | 1/9/2014 | 1/9/2014 | 1/9/2014 9:38:55 AM | | PASS |
|
|
No exterior construction activity or earthwork observed. There are ACHD Boise Ave road stockpiles in front of site at this time- not associated with house project. No corrections required.
|
ESC13-00930
| General Inspection | 1/9/2014 | 1/9/2014 | 1/9/2014 9:32:11 AM | | PASS |
|
|
All material contained within site. Permit posted on front gate. No track out visible.
|
ESC12-00845
| General Inspection | 1/9/2014 | 1/9/2014 | 1/9/2014 8:47:06 AM | | PASS |
|
|
Work on second portion of house in progress. Front and back have been mostly landscaped. No violations observed. Two ESC permits cover this project
|