ELE18-04361
| Electrical Rough-In | 1/8/2019 | 1/9/2019 | 1/9/2019 2:22:14 PM | P | PASS |
|
|
Ceiling inspection Phone #: ###-#### Inspection requested via web by Kevin Perez Grid rough in ok cover
|
ELE18-03418
| Final | 1/9/2019 | 1/9/2019 | 1/9/2019 1:48:14 PM | P | PASS |
|
|
Contact John Mittleider for final sign off for occupancy. Phone #: ###-#### Inspection requested via web by Tom Betty Final ok
|
ELE18-04262
| Electrical Rough-In | 1/9/2019 | 1/9/2019 | 1/9/2019 1:02:47 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Grid complete rough in ok cover
|
ELE18-04645
| Electrical Rough-In | 1/8/2019 | 1/9/2019 | 1/9/2019 12:18:25 PM | A | PASS |
|
|
underground, Phone #: ###-#### Inspection requested via web by Debby Pierce Permit has been changed to the core and shell building permit. Underground on south side run along foundation rough in ok cover
|
ELE18-02369
| Electrical Rough-In | 1/7/2019 | 1/9/2019 | 1/9/2019 11:07:55 AM | A | PASS |
|
|
WALL ROUGH-IN INSPECTION FOR FIRST AND FOURTH FLOOR. CALL JOEY C AT ###-#### PRIOR TO ARRIVAL. Phone #: ###-#### Inspection requested via web by Scott Campbell Informed seperate electrical permit required for elevators. Level 1 mail room, demizing wall, east exterior wall only. No stairway walls. Level 4 bathrooms and corridor as noted on contractor print wall rough in ok cover
|
ELE18-01608
| Electrical Rough-In | 1/8/2019 | 1/9/2019 | 1/9/2019 10:07:42 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud Central and western underground of west area as noted on contractor print rough in ok cover.
|
ELE19-00093
| Rough-In Permanent Service | 1/8/2019 | 1/9/2019 | 1/9/2019 9:31:51 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Bob Glenn Rough in ok cover p/s u/g n ok
|
ELE18-03512
| Final | 1/8/2019 | 1/9/2019 | 1/9/2019 8:54:21 AM | A | PASS |
|
|
Code 4224 Phone #: ###-#### Inspection requested via web by Bob Glenn Final ok
|