BLD97-01312
| INSP - Footings | 9/30/1997 | 10/1/1997 | 10/2/1997 12:00:00 AM | A | PART |
|
|
10/01/97 407 - special inspection required.
|
BLD97-01312
| INSP - Miscellaneous | 9/30/1997 | 10/1/1997 | 10/2/1997 12:00:00 AM | A | PART |
|
|
10/01/97 407 - PRECAST WALLS, special inspection required.
|
BLD97-02165
| INSP - Final | 9/24/1997 | 10/1/1997 | 10/2/1997 12:00:00 AM | P | CANC |
|
|
10/01/97 407 - Scheduled by Hello! on 09/24/97 at 11:07:55. this inspection is needed for 10/2/97.
|
BLD97-02193
| INSP - Framing/Rough-in | 10/1/1997 | 10/1/1997 | 10/2/1997 12:00:00 AM | P | PART |
|
|
10/01/97 407 - left correction.
|
BLD97-02473
| INSP - Framing/Rough-in | 10/1/1997 | 10/1/1997 | 10/1/1997 12:00:00 AM | | PART |
|
|
/ / 407 - re-insp.ok to sheet rock except for rear wall. waiting for e
|
BLD96-02395
| INSP - Letter of compliance | 10/1/1997 | 10/1/1997 | 10/1/1997 12:00:00 AM | | PASS |
|
|
/ / 407 - LC#12834
|
BLD96-02395
| INSP - Letter of compliance | 10/1/1997 | 10/1/1997 | 10/1/1997 12:00:00 AM | | PASS |
|
|
/ / 407 - LC#12834
|
BLD97-01651
| INSP - Wall cover | 9/30/1997 | 10/1/1997 | 10/1/1997 12:00:00 AM | A | PASS |
|
|
10/01/97 407 - SHEER WALL IN THE BASEMENT. This wall completes foundatio engineer. also attached to enginering was rebar #4 ok at a tall section wall. This now completes foudation.
|
BLD97-02473
| INSP - Energy code compliance | 9/30/1997 | 10/1/1997 | 10/1/1997 12:00:00 AM | A | PASS |
|
|
10/01/97 407 - Scheduled by Hello! on 09/30/97 at 15:08:55. insulation ok still have corrction on framing,they will recall forapprov cover.
|
BLD97-02228
| INSP - Framing/Rough-in | 9/30/1997 | 10/1/1997 | 10/1/1997 12:00:00 AM | A | PART |
|
|
10/01/97 407 - left corrections. ok to insulate.
|
MEC97-02616
| INSP - Rough-in & Gas Pressure | 10/1/1997 | 10/1/1997 | 10/1/1997 12:00:00 AM | P | PASS |
|
|
10/01/97 407 -
|