ESC10-00504
| General Inspection | 9/17/2010 | 10/1/2010 | 10/1/2010 3:22:10 PM | P | PART |
|
|
Re-inspect hillside above the retaining walls. Unchanged no problems observed.
|
ESC10-00743
| Site Preparation | 10/1/2010 | 10/1/2010 | 10/1/2010 2:26:42 PM | | PASS |
|
|
The site appears to be in compliance.
|
ESC10-00643
| General Inspection | 9/24/2010 | 10/1/2010 | 10/1/2010 10:48:40 AM | P | PART |
|
|
Verbal to RP, need to install sediment barriers at misc locations to reduce runoff with forecasted rain. Backfilled elevation has been completed but seeding and installation of slope has not been done at the time of this inspection. Access road has bare ground. Final stabilzation is needed on all bare ground.
|
ESC10-00672
| Conference | 9/29/2010 | 10/1/2010 | 10/1/2010 9:59:23 AM | A | DONE |
|
|
9:00 A.M.: Met with ACHD, (Tom D.), Inspector 460, RP (Kevin A.) and two other reps from Hunter Homes. Reviewed Federal and local regulations. Handed a copy of the local general ESC conditions to the RP. Compliance is expected.
|
ESC10-00682
| Site Preparation | 10/1/2010 | 10/1/2010 | 10/1/2010 7:42:44 AM | | CANC |
|
|
Inspector 450 passed on 9/28
|
ESC10-00742
| Site Preparation | 10/1/2010 | 10/1/2010 | 10/1/2010 7:42:17 AM | | CANC |
|
|
Inspector 301 passed on 9/29
|