BLD11-00907
| FIRE-Final Inspection | 10/1/2013 | 10/1/2013 | 10/2/2013 10:39:17 AM | P | PASS |
|
|
Fire life safety inspection passed. *Note- no signature card available on site*
|
FIR13-00397
| INSP-Final Inspection | 9/30/2013 | 10/1/2013 | 10/1/2013 4:40:27 PM | P | PASS |
|
|
Previous correction items finished. Reinspection passed. Fire alarm permit finaled.
|
FIR13-00170
| INSP-Final Inspection | 9/30/2013 | 10/1/2013 | 10/1/2013 3:22:41 PM | A | PART |
|
|
Completed fire alarm testing for buildings 8, 9, 10, and 11. Also finished reinspection for previous correction items at building 4. Correction and adjustment items noted today include; non-functional visual notification at ADA unit 1013, plans show incorrect room numbers for FACP units in buildings 6 and 9, MP stations for panel at buildings 5,6, and 7 did not activate horn strobes.
|
FIR13-00305
| INSP-Final Inspection | 9/30/2013 | 10/1/2013 | 10/1/2013 1:07:26 PM | A | PART |
|
|
Completed walkthrough- Need to install missing heads at the garage/riser areas, secure control valves at the riser, include finish pack with spare heads, calc sticker, etc. Flow switch tested okay, one missing escutcheon installed while on site. Need to provide thermal barrier or meet conditions for exposed CPVC pipe at the ground level unfinished bedroom, family room, WIC and under stair storage areas.
|
FIR13-00387
| INSP-Final Inspection | 9/30/2013 | 10/1/2013 | 10/1/2013 1:02:16 PM | A | PASS |
|
|
Previous correction item verified for completion. Final walkthrough passed. Fire sprinkler permit finaled.
|
BLD13-02149
| FIRE-Final Inspection | 9/30/2013 | 10/1/2013 | 10/1/2013 1:00:50 PM | A | PASS |
|
|
Fire life safety inspection completed acceptable.
|
FIR13-00527
| INSP-Final Inspection | 9/30/2013 | 10/1/2013 | 10/1/2013 12:59:54 PM | A | PASS |
|
|
Fire sprinkler work passed both rough-in and final inspections. Permit finaled.
|
BLD13-02382
| FIRE-Final Inspection | 9/30/2013 | 10/1/2013 | 10/1/2013 12:57:31 PM | A | PASS |
|
|
Life safety inspection completed satisfactory. PFE at the mezzanine level to be installed on a bracket as discussed.
|