Inspections for the day of: Thursday, October 1, 2015.
Number of inspections: 3
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorKatie Marron
TitleFIRE INSPECTOR
Phone #395-7809
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
NAF15-00014 INSP-Alarm Testing10/1/201510/1/201510/1/2015 5:01:12 PMPPASS
Fire alarm system tested besides devices on south west side. Flow switches tested manually (no flow). Partial final. Elevator 2nd and 3rd floor recall still to be conducted.
NAF15-00006 INSP-Final9/30/201510/1/201510/1/2015 5:00:47 PMAPART
Partial final complete for North East side. To be verified at full final, heads in bathroom changed to intermediate and one head in 2nd floor hallway @ north east side changed to intermediate due to proximity to heat device. Also flow test and forward flow to be tested.
NAF15-00024 INSP-Supply line flush10/1/201510/1/201510/1/2015 2:35:46 PMPDONE
No flush, underground cover inspection. Depth is good until land slopes down to the pump house. Contractor verified that Owner ok to berm up ground there to reach appropriate cover, verify 6"-1' berm at final.