FIR15-00601
| INSP-Sprinkler Rough-in | 10/1/2015 | 10/1/2015 | 10/1/2015 2:21:00 PM | P | FAIL |
|
|
Contractor requested inspection for rough to cover inspection on the hard lids, no hard lids approved for cover until upright head coverage is adjusted/corrected, multiple pockets above hard lids not covered and upright heads overspaced.
|
FIR15-00599
| INSP-Final Inspection | 10/1/2015 | 10/1/2015 | 10/1/2015 11:54:03 AM | A | PASS |
|
|
Final fire alarm inspection passed/complete
|
FIR15-00112
| INSP-Sprinkler Rough-in/Hydro | 10/1/2015 | 10/1/2015 | 10/1/2015 10:35:02 AM | P | PASS |
|
|
Rough to cover inspection passed/complete for 3rd floor, approved for cover. 200 psi hydrostatic test passed/complete for 3rd floor.
|
FIR15-00112
| INSP-Sprinkler Rough-in | 10/1/2015 | 10/1/2015 | 10/1/2015 10:17:54 AM | P | PASS |
|
|
Rough-in inspection for fourth floor passed/complete
|
FIR15-00672
| INSP-Sprinkler Rough-in/Hydro | 9/30/2015 | 10/1/2015 | 10/1/2015 10:16:07 AM | A | PASS |
|
|
Rough to cover inspection passed/complete, approved for cover
|
BLD15-03518
| FIRE-Final Inspection | 9/30/2015 | 10/1/2015 | 10/1/2015 9:59:55 AM | A | PASS |
|
|
Life fire safety passed/complete
|
FIR15-00112
| INSP-Final Inspection | 9/29/2015 | 10/1/2015 | 10/1/2015 9:45:18 AM | A | CANC |
|
|
Scheduled as a final inspection, needed to be scheduled for a rough-in/hydro, inspection, current inspection request rescheduled.
|