Inspections for the day of: Thursday, October 1, 2015.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR15-00601 INSP-Sprinkler Rough-in10/1/201510/1/201510/1/2015 2:21:00 PMPFAIL
Contractor requested inspection for rough to cover inspection on the hard lids, no hard lids approved for cover until upright head coverage is adjusted/corrected, multiple pockets above hard lids not covered and upright heads overspaced.
FIR15-00599 INSP-Final Inspection10/1/201510/1/201510/1/2015 11:54:03 AMAPASS
Final fire alarm inspection passed/complete
FIR15-00112 INSP-Sprinkler Rough-in/Hydro10/1/201510/1/201510/1/2015 10:35:02 AMPPASS
Rough to cover inspection passed/complete for 3rd floor, approved for cover. 200 psi hydrostatic test passed/complete for 3rd floor.
FIR15-00112 INSP-Sprinkler Rough-in10/1/201510/1/201510/1/2015 10:17:54 AMPPASS
Rough-in inspection for fourth floor passed/complete
FIR15-00672 INSP-Sprinkler Rough-in/Hydro9/30/201510/1/201510/1/2015 10:16:07 AMAPASS
Rough to cover inspection passed/complete, approved for cover
BLD15-03518 FIRE-Final Inspection9/30/201510/1/201510/1/2015 9:59:55 AMAPASS
Life fire safety passed/complete
FIR15-00112 INSP-Final Inspection9/29/201510/1/201510/1/2015 9:45:18 AMACANC
Scheduled as a final inspection, needed to be scheduled for a rough-in/hydro, inspection, current inspection request rescheduled.