BLD13-00166
| BLD-Conference | 10/2/2014 | 10/3/2014 | | A | |
|
|
|
BLD14-00819
| BLD-Framing/Rough-in | 10/10/2014 | 10/10/2014 | 10/10/2014 4:13:32 PM | P | FAIL |
|
|
Please inspect the 3rd floor framing
Thanks Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. Correction notice posted.
|
BLD14-00819
| BLD-Energy code compliance | 10/9/2014 | 10/10/2014 | 10/10/2014 4:12:49 PM | P | PASS |
|
|
Please contact Vicky to ensure access and can meet on site ###-####. Set for PM to ensure insulation is complete. Also will have plans for the 2nd floor TI on site.
Thanks Dave ###-#### Phone #: ###-#### Inspection requested via web by David Moorhouse. Ok to sheet rock first floor only, except for columns and underneath stair treads.
|
BLD14-00457
| BLD-Final | 10/10/2014 | 10/10/2014 | 10/10/2014 2:16:31 PM | P | NR |
|
|
Brian Phone #: ###-####. Needs zoning and other trades first.
|
BLD14-01545
| BLD-Footing | 10/9/2014 | 10/10/2014 | 10/10/2014 2:15:59 PM | P | PART |
|
|
Mike Phone #: ###-####. Work in progress. Will have special inspection.
|
BLD14-02892
| BLD-Final | 10/9/2014 | 10/10/2014 | 10/10/2014 12:44:29 PM | P | PART |
|
|
Dan-please call 20 minutes prior to meet Phone #: ###-####. Ok for temp occ.
|
BLD14-00819
| BLD-Energy code compliance | 10/10/2014 | 10/10/2014 | 10/10/2014 11:18:15 AM | A | CANC |
|
|
. Moved to pm.
|
BLD14-02865
| BLD-Final | 10/9/2014 | 10/10/2014 | 10/10/2014 11:17:54 AM | A | FAIL |
|
|
Bert-please call to meet-would like early Phone #: ###-####. Cover all exposed electrical outlets, Also noted that tenant has run air compressor lines, installed air hose reels and posiibly an air compressor. Per scope of work noted on permit, no new work is authorized under this permit.
|
BLD14-01764
| BLD-Framing/Rough-in | 10/9/2014 | 10/10/2014 | 10/10/2014 10:26:42 AM | A | PASS |
|
|
Pat Phone #: ###-####
|
BLD14-02274
| BLD-Framing/Rough-in | 10/9/2014 | 10/10/2014 | 10/10/2014 9:55:09 AM | A | PASS |
|
|
Look at the 3 hour exterior window infills. Phone #: ###-#### Inspection requested via web by Bob Thornton. 3hr. exterior window infills at prior loading dock location.
|