Inspections for the day of: Friday, October 11, 2013.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD12-03195 FIRE-Final Inspection10/11/201310/11/201310/11/2013 3:36:15 PMPPASS
life safety passed
BLD13-02082 FIRE-Final Inspection10/11/201310/11/201310/11/2013 3:25:30 PMPPASS
life safety passed
BLD13-02662 FIRE-Final Inspection10/10/201310/11/201310/11/2013 3:15:15 PMPFAIL
Provide single action hardware for the main exit, provide correct size fire extinguisher with current inspection tag and provide new address numbers that are 4" min. as discussed.
BLD13-00645 FIRE-Conference10/10/201310/11/201310/11/2013 3:09:39 PMADONE
Greg Baisch and I discussed the placement of the exit signs that may be blocked by ducting and the need for the fire hydrant to be rotated so that the 5" barrel does not face a parking space.
FIR13-00374 INSP-Final Inspection10/11/201310/11/201310/11/2013 3:01:46 PMPPASS
Permit finaled
FIR13-00495 INSP-Final Inspection10/11/201310/11/201310/11/2013 1:51:36 PMPPASS
Permit finaled.
FIR13-00338 INSP-Final Inspection10/10/201310/11/201310/11/2013 12:54:50 PMAPASS
Permit finaled. Forward flush passed.
BLD13-01323 FIRE-Final Inspection10/10/201310/11/201310/11/2013 12:52:30 PMAFAIL
Smoke alarms need to be located no closer than 3' from bathrooms with a shower or tub. This happens in three apartments. Post signage on riser room door.
FIR13-00441 INSP-Sprinkler Rough-in10/10/201310/11/201310/11/2013 10:37:13 AMAPASS
Mezzanine piping is ok to cover.. I noted that light fixtures may block pendant heads based on flex/wiring locations next to pendants.
FIR13-00505 INSP-Sprinkler Rough-in10/10/201310/11/201310/11/2013 10:34:39 AMAPASS
See the city approved plans for restroom piping that is ok to cover
BLD13-02441 FIRE-Final Inspection10/9/201310/11/201310/11/2013 9:39:20 AMAPASS
Life safety passed. I spoke to Tim about the need to maintain a 6" flue space within the rachking and he also agreed to remove the solid shelving. Also per TIm the racking not shown on the plans is an assembly area and is temporary as well.
FIR13-00342 INSP-Sprinkler Rough-in10/10/201310/11/201310/11/2013 8:01:29 AMAPASS
rough-in and tenting inspection passed. Piping can be covered.
FIR13-00280 INSP-Final Inspection10/10/201310/11/201310/10/2013 2:00:25 PMACANC
Please call Jeremy at ###-#### with inspection time Phone #: ###-#### >> Inspection requested via web by Lori Brungardt Inspection cancelled from web by: Lori Brungardt