BLD19-03591
| BLD-Final | 10/10/2019 | 10/11/2019 | 10/11/2019 4:09:15 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Jeff Higgins//racking installed per plans and engineering//third party inspection of post installed anchors was approved and documents reviewed onsite//
|
BLD19-01385
| BLD-Blower Door Test Results | 10/11/2019 | 10/11/2019 | 10/11/2019 4:03:00 PM | P | DONE |
|
|
4.5 ACH 50 1375 CFM @ 50 pa
|
BLD19-01385
| BLD-Final | 10/11/2019 | 10/11/2019 | 10/11/2019 4:01:00 PM | P | PASS |
|
|
Garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle//corrections made//
|
BLD19-01385
| DOC - Permit Finaled | 10/11/2019 | 10/11/2019 | 10/11/2019 4:00:38 PM | P | PASS |
|
|
|
BLD19-03209
| BLD-Framing/Rough-in | 10/11/2019 | 10/11/2019 | 10/11/2019 3:54:33 PM | P | PART |
|
|
Tom Phone #: ###-####//moved wall 10 inches//new electrical inspection was completed//bracing ok//
|
BLD18-03784
| BLD-Aging Inspection | 10/11/2019 | 10/11/2019 | 10/11/2019 3:51:31 PM | | PASS |
|
|
Expires: 11/26/19
|
BLD19-02420
| BLD-Energy code compliance | 10/11/2019 | 10/11/2019 | 10/11/2019 3:24:10 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD19-01729
| BLD-Footing | 10/10/2019 | 10/11/2019 | 10/11/2019 2:52:49 PM | P | PASS |
|
|
Dane Phone #: ###-####
|
BLD19-01731
| BLD-Foundation | 10/10/2019 | 10/11/2019 | 10/11/2019 2:52:33 PM | P | PASS |
|
|
Dane Phone #: ###-####
|
BLD19-02011
| BLD-Foundation | 10/10/2019 | 10/11/2019 | 10/11/2019 2:22:17 PM | P | CANC |
|
|
Dane Phone #: ###-####//wall not set//will re-schedule//
|
BLD19-03934
| BLD-Footing | 10/11/2019 | 10/11/2019 | 10/11/2019 1:54:42 PM | P | FAIL |
|
|
Brandy Phone #: ###-####//pans show turned down continuous footings for foundaiton//piers were dug and do not reflect enginneering//
|
BLD19-00999
| DOC - Permit Finaled | 10/11/2019 | 10/11/2019 | 10/11/2019 1:35:12 PM | P | PASS |
|
|
|
BLD19-01048
| BLD-Framing/Rough-in | 10/11/2019 | 10/11/2019 | 10/11/2019 12:57:22 PM | P | PASS |
|
|
###-#### Contact Corey Inspection requested via web by Eric Mccray//ok per changed plans for shear//framin ok per plans//ok to cover per Jack/mechanical--
|
BLD19-02972
| BLD-Framing/Rough-in | 10/10/2019 | 10/11/2019 | 10/11/2019 12:33:24 PM | P | CANC |
|
|
Call 15 mins ahead- Vedad Phone #: ###-####//need mechanical//will re schedule for monday//
|
BLD19-03224
| BLD-Final | 10/10/2019 | 10/11/2019 | 10/11/2019 12:21:30 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Michael La Pointe//roof appears to be installed within code requirements//
|
BLD19-03224
| DOC - Permit Finaled | 10/11/2019 | 10/11/2019 | 10/11/2019 12:21:04 PM | P | PASS |
|
|
|
BLD19-03816
| BLD-Framing/Rough-in | 10/11/2019 | 10/11/2019 | 10/11/2019 12:12:28 PM | P | PART |
|
|
Karen Phone #: ###-####//fixing hold downs while onsite--will be installed correctly//still need electrical rough ins//no cover of inside until electrical rough has passed//
|
BLD19-03208
| BLD-Final | 10/10/2019 | 10/11/2019 | 10/11/2019 11:13:26 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Michael La Pointe//roof appears to be installed within code requirements//
|
BLD19-03208
| DOC - Permit Finaled | 10/11/2019 | 10/11/2019 | 10/11/2019 11:13:02 AM | P | PASS |
|
|
|
BLD19-04020
| BLD-Final | 10/10/2019 | 10/11/2019 | 10/11/2019 10:45:29 AM | A | PASS |
|
|
Inspection requested via web by Richard Murray//roof appears to be installed within code requirements//
|
BLD19-04020
| DOC - Permit Finaled | 10/11/2019 | 10/11/2019 | 10/11/2019 10:44:59 AM | P | PASS |
|
|
|
BLD19-03941
| BLD-Footing | 10/10/2019 | 10/11/2019 | 10/11/2019 10:06:07 AM | A | PASS |
|
|
Phone #: 2088607548 >> Inspection requested via mobile web by Nick abernethy//footing ok per typical drawings//
|
BLD19-02238
| BLD-Wall Bracing | 10/10/2019 | 10/11/2019 | 10/11/2019 9:31:05 AM | A | PART |
|
|
Chris Phone #: ###-####//shear wall nailing ok per plans//hold downs and welding required for shear walls completed by third party//ok to cover pending third party approval of hold downs installation//
|
BLD18-02428
| BLD-Final | 10/10/2019 | 10/11/2019 | 10/11/2019 9:07:55 AM | A | FAIL |
|
|
George Phone #: ###-####//still need final for mechanical and gas fireplace prior to final inspection//left correction notice with owner onsite//
|
BLD18-02427
| BLD-Final | 10/10/2019 | 10/11/2019 | 10/11/2019 9:07:04 AM | A | FAIL |
|
|
George Phone #: ###-####//still needs mechanical final prior to final inspection//left correction notice with owner onsite//
|