PLM00-03231
| Final | 10/11/2000 | 10/12/2000 | 10/12/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 10/11/2000 at 14:45:49. Contact: ###-####.
|
PLM00-02912
| Plumbing Rough-in | 10/11/2000 | 10/12/2000 | 10/12/2000 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 10/11/2000 at 15:39:34. Contact: ###-####. restroom group area 3 gw ok 10/12/2000 3:44:56 PM
|
PLM00-03559
| Groundwork | 10/11/2000 | 10/12/2000 | 10/12/2000 12:00:00 AM | A | PART |
|
|
Scheduled by Inspector: 330 On 10/11/2000 iw gw test ok 10/12/2000 9:37:31 AM
|
PLM00-03573
| Plumbing Rough-in | 10/12/2000 | 10/12/2000 | 10/12/2000 12:00:00 AM | P | PASS |
|
|
R/I-- JENNIFER ----###-####
|
PLM99-03865
| Final | 10/12/2000 | 10/12/2000 | 10/12/2000 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 330 On 10/12/2000 bld 9 final ok loggers pond
|
PLM00-00096
| Plumbing Rough-in | 10/11/2000 | 10/12/2000 | 10/12/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 10/11/2000 at 11:26:23. Contact: ###-####.
|