Inspections for the day of: Friday, October 12, 2007.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR06-00011 INSP-Alarm Testing10/11/200710/12/200710/12/2007 3:52:44 PMPDONE
See mike timmermans notes for items tested today
FIR07-00848 INSP-Sprinkler Rough-in10/12/200710/12/200710/12/2007 3:51:26 PMPPASS
The sprinkler piping is ok to cover. The single head in the storage room is to be lowered so that it will provide coverage under the duct work.
BLD06-01695 FIRE-Final Inspection10/12/200710/12/200710/12/2007 2:47:35 PMPPASS
Life safety finaled
FIR07-00793 INSP-Final Inspection10/11/200710/12/200710/12/2007 2:43:43 PMPPASS
permit finaled
BLD07-02296 FIRE-Final Inspection10/12/200710/12/200710/12/2007 12:51:11 PMPFAIL
The two emergency lights in the main showroom still do not work.
FIR07-00565 INSP-Final Inspection10/12/200710/12/200710/12/2007 12:37:21 PMPPASS
Permit finaled
FIR07-00079 INSP-Final Inspection10/12/200710/12/200710/12/2007 12:36:41 PMPPASS
permit finaled
FIR07-00130 INSP-Final Inspection10/11/200710/12/200710/12/2007 12:31:54 PMAPASS
permit finaled
FIR07-00800 INSP-Sprinkler Rough-in10/11/200710/12/200710/12/2007 11:44:52 AMAPASS
The sprinkler piping as marked with todays date is ok to cover.
FIR05-00536 INSP-Final Inspection10/11/200710/12/200710/12/2007 11:03:37 AMAPASS
The fourth and fifth floor sprinkler systems are ready to final except the alarm interconnections need tested.
BLD07-01239 FIRE-Final Inspection10/11/200710/12/200710/12/2007 12:00:00 AMACANC
william Phone #: ###-####