Inspections for the day of: Wednesday, October 12, 2016.
Number of inspections: 2
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorKatie Marron
TitleFIRE INSPECTOR
Phone #395-7809
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD15-03610 FIRE-Final Inspection10/11/201610/12/201610/12/2016 3:51:44 PMPPASS
Life Safety Pass.
NAF16-00023 INSP-Sprinkler Rough-in10/11/201610/12/201610/12/2016 11:14:40 AMAPART
Rough-in inspection for grid ceiling areas:
-verified 'OK' north stairwell 2nd floor
-verified 'OK' first floor with exception of a dozen drops that were not in yet (heads were circled on drawings)
-verified 'ok' center office spacing issue previously noted.

Still Pending:
- 2nd flr Drop ceiling for hallway in front of elevator and apartments
- 2nd floor protector on upright
- 2nd flr mechanical room spaced with 5' issue
- 1st flr dozen of drop ceiling drops