Inspections for the day of: Thursday, October 12, 2017.
Number of inspections: 24
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD16-04278 FIRE-Final Inspection10/11/201710/12/201710/12/2017 1:47:23 PMPPASS
Life safety passed

Kelly Phone #: ###-####
BLD17-02893 FIRE-Final Inspection10/12/201710/12/201710/12/2017 1:36:39 PMPCANC
To be rescheduled for tomorrow due to the fire alarm not being ready and I need verification from an engineer that the smoke evac system is still functional/installed as designed.

Troy Phone #: ###-####
FIR17-00539 INSP-Sprinkler Rough-in10/11/201710/12/201710/12/2017 12:45:58 PMPPASS
Rough-in passed. Piping can be covered.
FIR16-00821 INSP-Sprinkler Rough-in10/12/201710/12/201710/12/2017 12:07:49 PMPPASS
Remaining piping in the east most building can be covered. Insulation has been added to the combustible concealed spaces.
BLD16-03633 FIRE-Final Inspection10/12/201710/12/201710/12/2017 12:07:00 PMPFAIL
Repair the exit sign/emergency light and remove the thumb turn deadbolt at the exit door.
FIR17-00365 INSP-Supply line flush10/12/201710/12/201710/12/2017 11:44:22 AMPPASS
Underground supply line flush passed
FIR17-00433 INSP-Supply line flush10/11/201710/12/201710/12/2017 11:44:00 AMPCANC
Wrong permit number called in
FIR17-00433 INSP-Sprinkler Rough-in10/11/201710/12/201710/12/2017 11:28:42 AMAPASS
The earth quake bracing has been corrected. The branchline siesmic restraints have been added and the east facing extended coverage dry sidewall has been piped. Lower level piping can be covered except where the piping penatrates out to the front entry canopy
FIR17-00587 INSP-Sprinkler Rough-in10/11/201710/12/201710/12/2017 10:17:56 AMAPART
Underground supply piping is ok to bury except for the stub-in to the building which still needs a thrust block poured for the "in building riser".
FIR17-00568 INSP-Sprinkler Rough-in10/11/201710/12/201710/12/2017 9:02:36 AMAPASS
Rough-in passed. Piping can be covered.
BLD17-03165 FIRE-Final Inspection10/11/201710/12/201710/12/2017 8:29:09 AMAPASS
Life safety passed.

Please call Sid ###-####
BLD17-02257 FIRE-Final Inspection10/11/201710/12/201710/12/2017 8:28:45 AMAPASS
Life safety passed

Dave Phone #: ###-####
BLD17-01782 FIRE-Final Inspection10/11/201710/12/201710/12/2017 8:28:20 AMAPASS
life safety passed

Dave Phone #: ###-####
BLD16-04227 FIRE-Final Inspection10/11/201710/12/201710/12/2017 8:27:58 AMAPASS
Life safety passed.

Dave Phone #: ###-####
FIR17-00511 INSP-Final Inspection10/11/201710/12/201710/12/2017 8:13:54 AMAPASS
Permit finaled
FIR17-00227 INSP-Final Inspection10/10/201710/12/201710/12/2017 7:39:32 AMAPASS
Permit finaled.
BLD16-02954 FIRE-Final Inspection10/11/201710/12/201710/11/2017 2:17:49 PMAPASS
life safety passed

Tim Phone #: ###-####
BLD16-02953 FIRE-Final Inspection10/11/201710/12/201710/11/2017 2:17:26 PMAPASS
life safety passed

Tim Phone #: ###-####
BLD16-01617 FIRE-Final Inspection10/11/201710/12/201710/11/2017 2:17:04 PMAPASS
life safety passed

Tim Phone #: ###-####
BLD16-02952 FIRE-Final Inspection10/11/201710/12/201710/11/2017 2:16:38 PMAPASS
Life safety passed.

Tim Phone #: ###-####
BLD16-02951 FIRE-Final Inspection10/11/201710/12/201710/11/2017 2:16:12 PMAPASS
Life safety passed

Tim Phone #: ###-####
BLD16-02948 FIRE-Final Inspection10/11/201710/12/201710/11/2017 2:15:50 PMAPASS
Life safety passed.

Tim Phone #: ###-####
BLD16-02950 FIRE-Final Inspection10/11/201710/12/201710/11/2017 2:15:27 PMAPASS
Life safety passed.

Tim Phone #: ###-####
BLD16-02949 FIRE-Final Inspection10/11/201710/12/201710/11/2017 2:15:07 PMAPASS
Life safety passed.

Tim Phone #: ###-####