FIR10-00425
| INSP-Sprinkler Rough-in/Hydro | 10/12/2010 | 10/13/2010 | 10/13/2010 3:12:54 PM | P | FAIL |
|
|
UG fire supply line hydrostatic test failed due to pressure loss below 200 psi at the guage.
|
FIR10-00425
| INSP-Sprinkler Rough-in/Hydro | 10/13/2010 | 10/13/2010 | 10/13/2010 3:11:33 PM | A | PART |
|
|
Underground fire supply line is approved for bury. Need to provide method for seismic clearance at the floor slab. Discussed fire code review notes regarding PI valves and riser room ratings.
|
FIR10-00466
| INSP-Sprinkler Rough-in | 10/13/2010 | 10/13/2010 | 10/13/2010 3:08:32 PM | P | PART |
|
|
Rough-in passed inspection. Noted SSP heads at the office area are to remain per contractor by owner request.
|
FIR10-00457
| INSP-Sprinkler Rough-in | 10/13/2010 | 10/13/2010 | 10/13/2010 3:06:30 PM | P | PART |
|
|
Overhead fire sprinkler modifications are approved for cover at the drop ceilings.
|
BLD10-02398
| FIRE-Final Inspection | 10/12/2010 | 10/13/2010 | 10/13/2010 11:38:10 AM | A | PASS |
|
|
Correction verified for compliance. Fire life safety passed.
|
FIR10-00483
| INSP-Final Inspection | 10/12/2010 | 10/13/2010 | 10/13/2010 8:01:24 AM | P | CANC |
|
|
barry Phone #: ###-#### Inspection cancelled from web by: BARRY KENDALL
|