Inspections for the day of: Friday, October 13, 2017.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDan Ediger
TitlePLM-INSPECTOR
Phone #869-5166
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM17-03869 Water and/or Sewer10/12/201710/13/201710/13/2017 2:16:41 PMPPART
partial water/sewer Phone #: ###-#### Inspection requested via web by Katherine Creekbaum. Water service and sewer ok to cover.
No approved plans on the job. Spoke with the builder and explained they taking responsiblities for any changes required on the approved set. Grease trap needs 24 hour test.
PLM17-02643 Groundwork10/13/201710/13/201710/13/2017 1:07:58 PMPFAIL
Contact: Robert Church ###-#### Phone #: ###-#### Inspection requested via web by Brent Lacy.
Building drain and sewer are backgrading 1/2" per foot at the connection. Expose sewer and building drain to verify grade.
2. Add the addition of the backwater valve value to the permit.
PLM17-03942 Final10/13/201710/13/201710/13/2017 12:55:07 PMPPASS
For questions call James at number provided. Phone #: ###-#### Inspection requested via web by Ben Davis
PLM17-03977 Final10/13/201710/13/201710/13/2017 12:44:39 PMPPASS
Phone #: ###-#### Inspection requested via web by Vaughn Carlson
PLM16-01058 Sprinkler (Final)10/13/201710/13/201710/13/2017 11:52:04 AMPPASS
PLM17-03961 Final10/12/201710/13/201710/13/2017 11:11:16 AMANH
Garage Code 1977.
Customer will not be home. Permission to enter through the garage. See Garage code above. Call Bill with any questions. Phone #: ###-#### Inspection requested ..
via web by Ben Davis. Will reschedule and meet on the job for access
PLM17-03936 Final10/11/201710/13/201710/13/2017 11:03:17 AMAPASS
Phone #: ###-#### Inspection requested via web by John Hensley
PLM17-03937 Water Heater Final10/11/201710/13/201710/13/2017 10:54:32 AMAPASS
Please call John prior to arrival at ###-####. thank you! Phone #: ###-#### Inspection requested via web by Maira Napoles
PLM17-02434 Final10/12/201710/13/201710/13/2017 10:39:44 AMAPASS
BRECK IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
PLM17-03803 Water and/or Sewer10/13/201710/13/201710/13/2017 10:24:57 AMPPASS
Manufactured Home sewer and water hook up. Failed previously because it needed a backflow inspection. That is complete now. Thanks!! Phone #: ###-#### Inspection requested via web by Ashleigh Meligan
PLM17-03803 DOC - Permit Finaled10/13/201710/13/201710/13/2017 10:24:32 AMPPASS
PLM17-03856 Final10/10/201710/13/201710/13/2017 10:13:15 AMAFAIL
Phone #: ###-#### Inspection requested via web by Marisa Hone.
Support the 4" flue from the water heater to the vertical connection. Reschedule
PLM17-03963 Final10/12/201710/13/201710/13/2017 9:16:12 AMACANC
Ask for Angel onsite, Mr. Rooter technician Shane Merkley will not be onsite. Work has was completed 5/16-5/17/17 between two Mr. Rooter invoices, 58073361 and 58049560. The wall where work was done has been back filled, but Mr. Rooter has picture evidence of work before, while, and after it was done that can be emailed per inspector request. Phone #: ###-#### Inspection requested via web by Shane Loar.
Rescheduled for site meeting
PLM17-03944 Final10/12/201710/13/201710/13/2017 8:52:33 AMAPASS
Ben Taylor Phone #: ###-####
PLM17-03883 Water Heater Final10/10/201710/13/201710/11/2017 9:13:40 AMACANC
Please call Lynette prior to arrival at ###-####. Phone #: ###-#### >> Inspection requested via web by Maira Napoles Inspection cancelled from web by: Maira Napoles