FIR02-00373
| INSP-Sprinkler Rough-in/Hydro | 10/10/2002 | 10/14/2002 | 10/14/2002 12:00:00 AM | A | FAIL |
|
|
rough-in for the TI is ok but can not be finaled untill the shell is finaled 10/14/2002 4:25:30 PM
|
BLD02-00992
| FIRE-Final Inspection | 10/10/2002 | 10/14/2002 | 10/14/2002 12:00:00 AM | A | PASS |
|
|
fire life/safety finaled. The architect stated that the new wall above the ceiling is intended for security not a fire wall after I questioned the lack of fire smoke damper and cable tray holes 10/14/2002 10:50:35 AM
|
BLD02-01479
| FIRE-Final Inspection | 10/11/2002 | 10/14/2002 | 10/14/2002 12:00:00 AM | A | CANC |
|
|
contractor (douge) stated that he did not call for an inspection. Nobody called so I'm cancelling it 10/14/2002 4:26:24 PM
|
FIR02-00325
| INSP-Final Inspection | 10/11/2002 | 10/14/2002 | 10/14/2002 12:00:00 AM | A | FAIL |
|
|
verify dedicated electrical circuit to FACP has been completed, clean up wiring in the FACP, verify batteries in FACP are supervised after the panel gets cleaned up, duct smoke detectors do nto activate the fie smoke dampers as per the review comments, change labeling on the new tamper switch 10/14/2002 10:48:58 AM
|
FIR02-00162
| INSP-Final Inspection | 10/11/2002 | 10/14/2002 | 10/14/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 10/11/2002 at 14:18:55. Contact: ###-####. verify dedicated electrical circuit to FACP has been completed, clean up wiring in the FACP, verify batteries in FACP are supervised after the panel gets cleaned up, duct smoke detectors do nto activate the fie smoke dampers as per the review comments, change labeling on the new tamper switch 10/14/2002 10:49:08 AM
|
FIR02-00304
| INSP-Sprinkler Rough-in | 10/14/2002 | 10/14/2002 | 10/14/2002 12:00:00 AM | P | FAIL |
|
|
provide additional hangers in 1st floor corridor, provide 4 way eq bracing in the northwest corner of the 2nd floor, provide upright instead of a pendant head in the 1st floor electrical room, provide adequate sprinkler coverage over lobby/egress corridor on the 1st floor.
|
FIR02-00325
| INSP-Final Inspection | 10/11/2002 | 10/14/2002 | 10/14/2002 12:00:00 AM | P | CANC |
|
|
duplicate inspection. The contractor said he punched in the wrong button and forgot to cancell 10/14/2002 4:27:08 PM
|