FIR03-00202
| INSP-Final Inspection | 10/10/2003 | 10/14/2003 | 10/14/2003 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 10/10/2003 at 4:00:18 PM. Contact: ###-####. Call from Brian that they aren't ready and will reschedule for a later date 10/14/2003 9:49:33 AM
|
FIR03-00553
| INSP-Sprinkler Rough-in/Hydro | 10/13/2003 | 10/14/2003 | 10/14/2003 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 10/13/2003 at 3:07:39 PM. Contact: ###-####. installed per plans; ceiling grid not installed so flex drops aren't completed; okay to cover; sprinkler system requires annual inspection; need sign on riser room door 10/14/2003 8:30:46 AM
|
BLD03-00923
| FIRE-Final Inspection | 10/14/2003 | 10/14/2003 | 10/14/2003 12:00:00 AM | P | NR |
|
|
Scheduled by a contractor via Hello! on 10/14/2003 at 7:38:49 AM. Contact: ###-####. Wayne called and said the sprinkler bracing isn't complete 10/14/2003 3:23:49 PM
|
FIR03-00203
| INSP-Final Inspection | 10/14/2003 | 10/14/2003 | 10/14/2003 12:00:00 AM | P | NR |
|
|
Scheduled by a contractor via Hello! on 10/14/2003 at 7:40:10 AM. Contact: ###-####. Wayne called and said the sprinkler bracing isn't complete 10/14/2003 3:24:09 PM
|
FIR03-00471
| INSP-Conference | 10/14/2003 | 10/14/2003 | 10/14/2003 12:00:00 AM | P | PART |
|
|
stopped by the school and there are boxes with wire at locations where smoke detectors would be installed for release of new doors at serving line 10/14/2003 2:59:38 PM
|
FIR03-00446
| INSP-Alarm Testing | 10/10/2003 | 10/14/2003 | 10/14/2003 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 10/10/2003 at 11:38:39 AM. Contact: ###-####. strobe not working in corridor 204b; device descriptors don't match acutual assigned room numbers (signs on wall next to rooms) and this was identified at the final inspection of the first phase to open the terminal 10/14/2003 2:15:52 PM
|