Inspections for the day of: Monday, October 15, 2007.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00536 INSP-Final Inspection10/15/200710/15/200710/19/2007 3:59:05 PMPCANC
Duplicate inspection
BLD05-00635 FIRE-Final Inspection10/15/200710/15/200710/16/2007 4:45:10 PMPFAIL
The exterior emergency lighting needs finished, the fire alarm permit satified and the sprinklers in the new canopy addressed.
FIR06-00011 INSP-Alarm Testing10/15/200710/15/200710/16/2007 12:24:45 PMPDONE
See mike timmermans notes for items tested and remaining.
FIR07-00838 INSP-Sprinkler Rough-in10/12/200710/15/200710/15/2007 4:59:12 PMAPASS
Sprinkler piping is ok to cover.
BLD07-02302 FIRE-Final Inspection10/15/200710/15/200710/15/2007 2:19:01 PMPPASS
life safety passed
FIR05-00536 INSP-Sprinkler Rough-in10/12/200710/15/200710/15/2007 1:55:10 PMAPASS
Overhead hydro test for 7th and 8th floors passed.
FIR07-00163 INSP-Sprinkler Rough-in/Hydro10/11/200710/15/200710/15/2007 10:38:15 AMAPART
OH Hydro Inspection on the three wet risers passed. The preaction hydro test failed. The riser/header and fdc still needs to be hydro tested.