Inspections for the day of: Wednesday, October 15, 2008.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBob Reichert
TitleELE-INSPECTOR
Phone #794-1923
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE08-02536 Electrical Rough-In10/15/200810/15/200810/15/2008 4:13:55 PMPPART
Requesting a partial underground inspection of the parking lot. Phone #: ###-#### Internet Inspection Request from: Dan Hardisty u/g anop ok to cover- west and north parts of building
ESC08-00583 General Inspection10/15/200810/15/200810/15/2008 3:16:39 PMAPASS
looked ok
ESC07-00796 General Inspection10/15/200810/15/200810/15/2008 3:15:45 PMAPASS
looked ok
ESC08-00457 General Inspection10/15/200810/15/200810/15/2008 3:14:25 PMPPASS
looked ok
ESC06-01299 General Inspection10/15/200810/15/200810/15/2008 3:13:30 PMPPASS
looked ok
ELE07-03307 Electrical Rough-In10/14/200810/15/200810/15/2008 2:14:29 PMPPASS
Contact: Neil Ramsey 10th thru 14th floors East & West Stairwells please Phone #: ###-#### Internet Inspection Request from: Deb Gooden stairwells floor 10 to 14 east and west ok to cover
ELE08-02771 Rough-In Permanent Service10/15/200810/15/200810/15/2008 1:18:43 PMPPASS
ready for inspection Phone #: ###-#### Internet Inspection Request from: gary batten corrections made, ri ok , p/s o/h rec ok, no esc this project
ELE08-02771 Final10/15/200810/15/200810/15/2008 1:03:58 PMPPASS
ready for inspection Phone #: ###-#### Internet Inspection Request from: gary batten ok to final, no esc this project
ELE08-02750 Electrical Rough-In10/14/200810/15/200810/15/2008 12:10:52 PMAPASS
have machines hooked up ready for inspection. marking plates on order for disconnects. office should be open at 9am Phone #: ###-#### Internet Inspection Request from: joe wheeler ric ok, owner is getting field evaluation for machines, will let know when set up for evaluation. Told owner electrical can final permit after evaluation done. Structural can do occupancy, since no place for electrical to sign. No esc this project
ELE08-02534 Electrical Rough-In10/14/200810/15/200810/15/2008 10:14:55 AMAPASS
This inspection will be for a partial wall rough in. Contact name is Mark Hood. Thank you and have a great day. Phone #: ###-#### Internet Inspection Request from: Laura Longshaw walls only anop, phase 2 ok to cover no esc this project
ELE07-00524 Final10/15/200810/15/200810/15/2008 9:39:56 AMAPASS
ok to final, no esc this project
ELE07-00557 ELE-Aging Inspection10/15/200810/15/200810/15/2008 9:37:17 AM DONE
see final, no esc this project
ELE07-00557 Final10/15/200810/15/200810/15/2008 9:36:51 AMAPASS
ok to final, no esc this project
ELE08-02310 Electrical Rough-In10/13/200810/15/200810/15/2008 9:35:19 AMAPASS
bob Phone #: ###-#### sanctuary walls and hard ceiling, phase 2, ok to cover
ELE08-02800 Permanent Service10/15/200810/15/200810/15/2008 8:55:51 AMAPASS
Inspection for new permanent service only. Phone #: ###-#### Internet Inspection Request from: Steve Craig p/s o/h rec ok
ELE08-01848 Final10/14/200810/15/200810/15/2008 8:07:20 AMAPASS
Final Electrical Inspection, Luke is contact Journeyman ###-#### Phone #: ###-#### Internet Inspection Request from: Beka Hereau ok to final, signed occupancy card, no esc this project