Inspections for the day of: Tuesday, October 15, 2013.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEvan Jenkins
TitleEROSION CONTROL MANAGER
Phone #794-3958
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC13-00291 General Inspection10/15/201310/15/201310/15/2013 2:07:22 PM PART
Contacted Chris Jensen via cell then talked verbally about sweeping up along Broad St. Also, contain power washing waters from entering the seepage bed from power washing sides of buildings.
Verbal Warning
ESC13-00230 General Inspection10/15/201310/15/201310/15/2013 12:30:16 PMPFAIL
Correction Notice Issued:
Sweep all streets to remove exess trackout. Remove Dirt Ramps throughout Project. Install 3 Construction Entrances per site plan
ESC12-00077 Site Final10/14/201310/15/201310/15/2013 12:27:36 PMAPART
Daniel-actually sub #3 Phone #: ###-####
3 Home Properties still need Re-vegetated. Concrete washout areas need to be removed along with garbage piles prior to officially Signing Off on the project. EJ 794.3958
ESC13-00938 Site Preparation10/15/201310/15/201310/15/2013 11:20:31 AMPPART
Kristy Phone #: ###-####
Install straw wattle along north side of project to protect Canal.
Sweep Street, install waddle along sidewalk
ESC13-00970 Site Preparation10/14/201310/15/201310/15/2013 10:55:10 AMAPASS
Justin Phone #: ###-####
BMP's Installed, Sand Windows Protected.
Stop Work Order Removed
ESC13-01036 Site Preparation10/14/201310/15/201310/14/2013 1:48:20 PMAPASS
Kevin Phone #: ###-####