PLM18-04227
| Water and/or Sewer | 10/15/2018 | 10/15/2018 | 10/15/2018 4:04:57 PM | P | PART |
|
|
Gary-sewer line only Phone #: ###-#### 1st 20 feet by roadway in off Sunset............ds
|
PLM17-03172
| Final | 10/12/2018 | 10/15/2018 | 10/15/2018 3:37:53 PM | P | PART |
|
|
Water meter Tie-In, area drain sub-rough, level 5 finish, level 4 finish. Phone #: ###-#### Inspection requested via web by Preston Langdon 5th floor and 4th floor completed.........water tie in done and backflows tested.........ds
|
PLM18-04332
| Groundwork | 10/15/2018 | 10/15/2018 | 10/15/2018 2:06:11 PM | P | PASS |
|
|
Garage bath room .. Phone #: ###-#### Inspection requested via web by Jerry Downer
|
PLM18-04147
| Plumbing Rough-in | 10/12/2018 | 10/15/2018 | 10/15/2018 1:48:35 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Brian Johansen
|
PLM17-04080
| PLM-Aging Inspection | 10/15/2018 | 10/15/2018 | 10/15/2018 9:50:13 AM | | PASS |
|
|
wip
|
PLM17-04391
| Pressure Test | 10/15/2018 | 10/15/2018 | 10/15/2018 9:47:43 AM | A | PART |
|
|
60 lb test on Gas to meter location...........partial only..........ds
|
PLM17-04391
| Plumbing Rough-in | 10/12/2018 | 10/15/2018 | 10/15/2018 9:47:25 AM | A | PART |
|
|
If there are any questions please contact Glen B. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann partial gas line test...........tested 60 lbs ok.......ds
|
PLM18-04327
| Plumbing Rough-in | 10/14/2018 | 10/15/2018 | 10/15/2018 9:37:08 AM | A | PASS |
|
|
Inspection requested via web by travis prawitz
|
PLM18-04323
| Final | 10/15/2018 | 10/15/2018 | 10/15/2018 9:23:33 AM | A | PASS |
|
|
Water service tested ok for cover..........called Suez and gave them info............ds
|
PLM18-04323
| Pressure Test | 10/14/2018 | 10/15/2018 | 10/15/2018 9:23:19 AM | A | PASS |
|
|
Niall, will be on site and test put on sunday afternoon Tks Phone #: ###-#### Inspection requested via web by niall magill water service tested ok for cover.........ds
|