Inspections for the day of: Monday, October 15, 2018.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEric Story
TitleELE-INSPECTOR
Phone #985-3493
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE18-03738 Electrical Rough-In10/15/201810/15/201810/15/2018 3:44:36 PMPCANC
Nothing to look at at thias time
ELE18-03944 Permanent Service10/15/201810/15/201810/15/2018 1:43:44 PMPPASS
Please arrive by 2pm if at all possible so we can get Idaho Power back out to reconnect. Thanks! Phone #: ###-#### Inspection requested via web by Same Electric
p/s o/h rec ok
ELE18-03659 Final10/12/201810/15/201810/15/2018 1:42:28 PMPPASS
This is ready to final off. Joe Kaminsky is contact at ###-####. thank you. Phone #: ###-#### Inspection requested via web by Debby Pierce
Final ok
ELE18-03924 Electrical Rough-In10/12/201810/15/201810/15/2018 1:41:36 PMPPASS
Phone #: ###-#### Inspection requested via web by Patrick Paz
Kitchen only ok to cover
ELE18-03931 Temporary Service10/12/201810/15/201810/15/2018 1:40:51 PMAPASS
This is overhead. If you have any questions please feel free to contact Darren ###-####. Thanks!!! Phone #: ###-#### Inspection requested via web by Clayton Morgan

t/s o/h n ok
ELE18-03865 Electrical Rough-In10/12/201810/15/201810/15/2018 12:43:18 PMAPASS
Taylor Barton "
###-####" Phone #: ###-#### Inspection requested via web by BRS PermittingVerified listing and scope of work on Solar Array install also did a conference on line side tap, If a disc of power is needed to perform tap the service will need to be redone to current code due to it not up to code ......
ELE18-03929 Conference10/12/201810/15/201810/15/2018 12:39:01 PMADONE
please call 1 hour before you go out so that i can meet you Phone #: ###-#### Inspection requested via web by Chris Berthelot
Discussed re-wiring whole house due to several open spices and j-boxes located behind sheetrock, contractor will re-wire as the liability is to high due to there could still be multiple areas with same issue.
ELE18-01179 Electrical Rough-In10/15/201810/15/201810/15/2018 12:21:21 PMPPASS
part roughin- Greg Phone #: ###-####
Back of house master,living, bath all ok to cover
ELE18-03930 Final10/12/201810/15/201810/15/2018 9:59:35 AMAPASS
It will be open. If you have any questions please feel free to contact Clay ###-####. Thanks!!! Phone #: ###-#### Inspection requested via web by Clayton Morgan
As per Rock Hudson final ok
Upstairs is for storage aat this time
ELE18-03938 Electrical Rough-In10/14/201810/15/201810/15/2018 9:47:10 AMAPASS
Ground works inspection Phone #: ###-#### Inspection requested via web by Don Conley
u/g to detached garage ok to cover
ELE18-03738 Permanent Service10/11/201810/15/201810/15/2018 9:42:55 AMACANC
Aaron Phone #: ###-####
ELE18-03797 Electrical Rough-In10/13/201810/15/201810/15/2018 9:42:09 AMAPASS
Phone #: ###-#### Inspection requested via web by Jason Wicks
Whole house rough-in ok to cover
ELE18-03797 Permanent Service10/15/201810/15/201810/15/2018 9:41:31 AMPPASS
Phone #: ###-#### Inspection requested via web by Jason Wicks
p/s o/h rec ok
ELE18-03922 Temporary Service10/12/201810/15/201810/15/2018 9:02:40 AMAPASS
Jeff Phone #: ###-####
t/s u/g n ok
ELE18-03923 Temporary Service10/12/201810/15/201810/15/2018 9:02:19 AMAPASS
Jeff Phone #: ###-####
t/s u/g n ok