FIR08-00653
| INSP-Sprinkler Rough-in/Hydro | 10/16/2008 | 10/16/2008 | 10/16/2008 5:55:11 PM | P | PART |
|
|
OH fire sprinkler system modifications are approved for cover at the drop ceilings, final pending ceiling tile and escutcheons.
|
BLD08-00572
| FIRE-Conference | 10/16/2008 | 10/16/2008 | 10/16/2008 5:54:12 PM | P | DONE |
|
|
Conference regarding status of work and final inspection schedule.
|
BLD08-02122
| FIRE-Final Inspection | 10/16/2008 | 10/16/2008 | 10/16/2008 5:53:13 PM | P | PASS |
|
|
Life safety inspection passed, max. occupant load sign to be posted prior to structural final as agreed, owner to maintain 2nd floor mechanical room clear of storage.
|
FIR08-00039
| INSP-Sprinkler Rough-in/Hydro | 10/16/2008 | 10/16/2008 | 10/16/2008 5:49:37 PM | A | PART |
|
|
Hydrostatic test for the wet and antifreeze systems east remodel area syst. #2 completed acceptable.
|
FIR06-00621
| INSP-Alarm Testing | 10/10/2008 | 10/16/2008 | 10/16/2008 5:48:02 PM | A | PART |
|
|
Tested smoke detectors at and above ceilings including door release and manual pull stations at the common corridors 1st and 2nd floors and electrical/mechanical areas on the 2nd floor. Noted overspaced smoke detection at the west 1st floor corridor and one incorrect address.
|
FIR08-00443
| FIR-Aging Inspection | 10/16/2008 | 10/16/2008 | 10/16/2008 5:42:17 PM | | DONE |
|
|
Work in progress, construction underway.
|