FIR13-00526
| INSP-Sprinkler Rough-in | 10/16/2013 | 10/16/2013 | 10/16/2013 5:06:53 PM | P | PART |
|
|
Completed inspection for pendent heads at grid ceilings throughout the 7th floor. Need to install additional coverage at two storage rooms per the approved plan and hazard category, blocked coverage adjacent to the structural column in SW office #3. Remainder of work okayed for cover.
|
BLD13-02305
| FIRE-Final Inspection | 10/16/2013 | 10/16/2013 | 10/16/2013 4:55:03 PM | P | PASS |
|
|
For verification of repairs and revised locations of EM lights.
|
BLD13-01229
| FIRE-Final Inspection | 10/16/2013 | 10/16/2013 | 10/16/2013 4:53:44 PM | A | NR |
|
|
Pending corrections as noted.
|
BLD13-02702
| FIRE-Sprinkler Rough-in | 10/16/2013 | 10/16/2013 | 10/16/2013 4:52:41 PM | A | PART |
|
|
Okay to cover overhead fire sprinkler work above the new grid ceiling.
|