FIR14-00219
| INSP-Final Inspection | 10/16/2014 | 10/16/2014 | 10/16/2014 4:56:33 PM | P | PASS |
|
|
Fire alarm permit work approved for final. Mag lock hardware at the NW door has been removed.
|
BLD14-01682
| FIRE-Final Inspection | 10/16/2014 | 10/16/2014 | 10/16/2014 4:50:40 PM | P | PASS |
|
|
Fire life safety inspection completed satisfactory.
|
BLD14-01632
| FIRE-Final Inspection | 10/16/2014 | 10/16/2014 | 10/16/2014 4:48:29 PM | P | PASS |
|
|
Fire life safety inspection completed. Contractor to finish signage and keyed lock at the main door prior to structural final.
|
BLD13-02927
| FIRE-Final Inspection | 10/16/2014 | 10/16/2014 | 10/16/2014 1:53:34 PM | P | PASS |
|
|
Fire life safety passed provided single action hardware is provided as discussed.
|
FIR14-00591
| INSP-Final Inspection | 10/16/2014 | 10/16/2014 | 10/16/2014 1:49:22 PM | P | PASS |
|
|
Fire sprinkler permit work passed final walkthrough.
|
BLD14-02397
| FIRE-Final Inspection | 10/13/2014 | 10/16/2014 | 10/16/2014 1:47:23 PM | A | FAIL |
|
|
Items necessary prior to final include; provide current certification for fire extinguishers on each floor level, revise door hardware at the main entry/exit to meet min. requirements- single motion, signage, etc.
|
BLD14-00888
| FIRE-Final Inspection | 10/14/2014 | 10/16/2014 | 10/16/2014 1:44:49 PM | A | PASS |
|
|
Previous correction items verified for completion. Fire life safety finaled.
|