ELE14-00855
| ELE-Aging Inspection | 10/16/2018 | 10/16/2018 | 10/17/2018 2:39:34 PM | | PASS |
|
|
final scheduled
|
ELE18-03926
| Final | 10/15/2018 | 10/16/2018 | 10/16/2018 3:22:37 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton...ok to final
|
ELE18-02922
| Final | 10/16/2018 | 10/16/2018 | 10/16/2018 3:09:49 PM | P | PART |
|
|
final for Office unit only interior Phone #: ###-#### Inspection requested via web by Todd Hall..interior of office ok...ok to move furniture in office
|
ELE18-02922
| Electrical Rough-In | 10/16/2018 | 10/16/2018 | 10/16/2018 3:08:55 PM | P | PASS |
|
|
ceiling grid Office unit Phone #: ###-#### Inspection requested via web by Todd Hall... ceiling grid in office ok to cover
|
ELE17-02625
| Conference | 10/15/2018 | 10/16/2018 | 10/16/2018 2:18:37 PM | P | PASS |
|
|
Charles Phone #: ###-####...discussed new service location, riser length, guide wire kit, sub panel feed
|
ELE18-03945
| Permanent Service | 10/15/2018 | 10/16/2018 | 10/16/2018 1:24:18 PM | P | PASS |
|
|
Service change Phone #: ###-#### Inspection requested via web by Lars Johnson... all in one outside, new riser, guide wire kit interior panel used as junction box-images final new grounding 2 ground rods p/s o/h reconnect ok
|
ELE18-02503
| Final | 10/16/2018 | 10/16/2018 | 10/16/2018 12:57:58 PM | P | NR |
|
|
Electrical final of industrial equipment Phone #: ###-#### Inspection requested via web by Paula Gratiot...will reschedule when can meet and go over scope of work
|
ELE18-03933
| Final | 10/16/2018 | 10/16/2018 | 10/16/2018 12:26:08 PM | P | PASS |
|
|
re-use of existing water heater circuit and turned to 110v for furnace. correct breaker and blanks installed in panel.
|
ELE18-02214
| Final | 10/16/2018 | 10/16/2018 | 10/16/2018 12:06:11 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by kendall bender...ok to final..no card on site
|
ELE18-03781
| Electrical Rough-In | 10/12/2018 | 10/16/2018 | 10/16/2018 10:35:16 AM | A | PASS |
|
|
Call Foreman 30-60 min ahead: Bryce Waterman Phone #: ###-#### Inspection requested via web by Rob Maes...UL listed equipment verified...line side tap with 30A breaker added to panel for generator back up
|
ELE18-02014
| Electrical Rough-In | 10/15/2018 | 10/16/2018 | 10/16/2018 9:46:04 AM | A | PASS |
|
|
Inspection for units: 102, 104, 140, 141, 204 Phone #: ###-#### Inspection requested via web by Harvey Reyna...ok to cover 5 rms requested
|
ELE18-03933
| Final | 10/15/2018 | 10/16/2018 | 10/16/2018 9:04:19 AM | A | CANC |
|
|
Convert old water heater circuit to furnace circuit. Above is Tenant # James. Please call Kelly at ###-#### if problems with access. Thank you Phone #: ###-#### Inspection requested via web by Kelly Felin...unable to meet in AM...rescheduled to PM at 3:30
|
ELE18-03946
| Electrical Rough-In | 10/15/2018 | 10/16/2018 | 10/16/2018 8:37:07 AM | A | PASS |
|
|
Bonding Phone #: ###-#### Inspection requested via web by Kevin Koomler...4 corners, cover, and 1 light...ok to cover
|
ELE18-03782
| Final | 10/12/2018 | 10/16/2018 | 10/15/2018 3:47:40 PM | P | PASS |
|
|
Foreman: Bryce Waterman Phone #: ###-#### Inspection requested via web by Rob Maes... finaled 10/15/18
|