ESC17-00018
| General Inspection | 10/16/2018 | 10/16/2018 | 10/18/2018 3:20:57 PM | P | PASS |
|
|
Subdivsion BMPs installed. LOts of earth work this week, subdivision will need sweeping end of week. Stormdrains have sediment protection. Concrete washouts provided.
|
ESC16-00489
| General Inspection | 10/16/2018 | 10/16/2018 | 10/18/2018 2:52:45 PM | | CANC |
|
|
|
ESC12-00403
| Site Final | 10/16/2018 | 10/16/2018 | 10/17/2018 6:11:28 PM | P | PASS |
|
|
Construction complete. No ESC requests. Former laydown areas now developed or have new use. ESC permit finaled.
|
ESC18-00392
| General Inspection | 10/10/2018 | 10/16/2018 | 10/17/2018 3:01:57 PM | A | PASS |
|
|
follow up inspection on correction requests.
Corrections requested completed. Perimter wattles installed. Run on diversion berm installed to prevent extra runoff from disturbed site. RP-GC onsite.
No new corrections requested.
|
ESC17-00793
| General Inspection | 10/16/2018 | 10/16/2018 | 10/17/2018 2:30:03 PM | | PASS |
|
|
WIP on exterior finish and landscaping. Sediment check bags by storm drain were maintained after storm event. No trackout or discharges from site. Near completion.
|
MIS18-00346
| ESC-Conference | 10/12/2018 | 10/16/2018 | 10/17/2018 2:23:51 PM | A | PEND |
|
|
Will call realtor and let them know they will need to control the disturbed areas from the text excavations.
|
MIS18-00375
| ESC-Conference | 9/24/2018 | 10/16/2018 | 10/17/2018 10:48:55 AM | A | CANC |
|
|
reassigned
|
ESC12-00403
| General Inspection | 10/16/2018 | 10/16/2018 | 10/16/2018 11:49:15 AM | | CANC |
|
|
|