FIR05-00389
| FIR-Aging Inspection | 10/17/2005 | 10/17/2005 | 10/19/2005 10:13:59 AM | | NR |
|
|
Jeff is going to check on job status
|
FIR05-00586
| INSP-Sprinkler Rough-in | 10/17/2005 | 10/17/2005 | 10/17/2005 4:25:19 PM | P | PART |
|
|
Underground supply piping is ok to cover from United Waters tie in up thrust block.
|
FIR05-00651
| INSP-Final Inspection | 10/17/2005 | 10/17/2005 | 10/17/2005 4:07:15 PM | P | FAIL |
|
|
Tested the batteries and phone lines and one duct smoke detector in Michaels. Phone line programming had to be changed so it could be supervised and horns didn't work
|
BLD05-02858
| FIRE-Final Inspection | 10/14/2005 | 10/17/2005 | 10/17/2005 2:43:06 PM | A | FAIL |
|
|
###-#### - larry No access to building
|
FIR05-00597
| INSP-Sprinkler Rough-in/Hydro | 10/17/2005 | 10/17/2005 | 10/17/2005 2:41:33 PM | P | CANC |
|
|
Contact Brian; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley
|
FIR05-00565
| INSP-Final Inspection | 10/17/2005 | 10/17/2005 | 10/17/2005 2:07:36 PM | P | FAIL |
|
|
The sprinkler heads that have been modified need hangers taken to the top of the structure and pendant heads are overspaced in two locations. See approved plans.
|
FIR05-00029
| INSP-Sprinkler Rough-in | 10/17/2005 | 10/17/2005 | 10/17/2005 1:21:32 PM | P | PASS |
|
|
Underground supply line is ok to cover
|
BLD05-02087
| FIRE-Final Inspection | 10/13/2005 | 10/17/2005 | 10/17/2005 9:59:12 AM | A | FAIL |
|
|
Provide indicators for the locks on the main exit doors, paint address numbers so they contrast with the building colors, lower fire extinguishers to 48" to top of handle and provide with current inspection tags, provide approved hardware on the other doors that have been modified. See plans for locations and remove all thumbturn locks, test the duct smoke detectors and provide with remote annunciators per the IMC. Use system sensor model #ssk451
|
BLD05-01657
| FIRE-Final Inspection | 10/14/2005 | 10/17/2005 | 10/17/2005 9:03:26 AM | A | PASS |
|
|
Life safety finaled
|