Inspections for the day of: Friday, October 17, 2008.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR04-00688 INSP-Conference10/17/200810/17/200810/21/2008 5:00:56 PMPDONE
Cancel permit...... Phone #: ###-#### Internet Inspection Request from: Jeff Walton NOTE: Request per contractor to void permit granted- Scope of work abandoned.
FIR05-00130 INSP-Final Inspection10/17/200810/17/200810/17/2008 5:38:44 PMPPEND
Check status.... Phone #: ###-#### Internet Inspection Request from: Jeff Walton
FIR05-00780 INSP-Final Inspection10/17/200810/17/200810/17/2008 5:35:48 PMPPASS
Permit finaled per activity completed 1/25/06.
FIR05-00420 INSP-Final Inspection10/17/200810/17/200810/17/2008 5:33:53 PMPPASS
Permit finaled per activity completed 3/14/06.
FIR08-00507 INSP-Final Inspection10/17/200810/17/200810/17/2008 5:27:05 PMPPASS
Repairs are complete, final fire alarm testing passed, permit finaled.
FIR07-00790 INSP-Final Inspection10/17/200810/17/200810/17/2008 5:26:22 PMPPASS
Fire sprinkler permit finaled.
FIR08-00039 INSP-Sprinkler Rough-in10/16/200810/17/200810/17/2008 2:03:13 PMPPART
Previous c/n items for the overhead rough-in have been corrected, install is okay for cover when main tie-ins have been finished.
BLD07-00954 FIRE-Final Inspection10/16/200810/17/200810/17/2008 1:59:29 PMAPART
Fire life safety completed acceptable, however project cannot be finaled until related fire alarm permit # FIR07-00807 is finaled.
BLD08-01991 FIRE-Final Inspection10/16/200810/17/200810/17/2008 1:57:24 PMAPASS
Fire life safety inspection passed.
FIR08-00444 FIR-Aging Inspection10/17/200810/17/200810/17/2008 1:56:14 PM DONE
Work in progress, construction underway.
FIR08-00388 INSP-Final Inspection10/16/200810/17/200810/17/2008 1:55:15 PMAPASS
Correction notice items verified for completion, fire sprinkler permit finaled.