BLD11-02288
| FIRE-Final Inspection | 10/17/2011 | 10/17/2011 | 10/17/2011 3:52:55 PM | P | PASS |
|
|
life safety passed
|
FIR11-00503
| INSP-Final Inspection | 10/14/2011 | 10/17/2011 | 10/17/2011 3:16:56 PM | P | FAIL |
|
|
Todays inspection was to finish up functional testing of the initiating devices. Due to my time constraints and only one contractor/tech we only had time to finish the second floor. Still need to check the portable classroom devices.
|
BLD11-01675
| FIRE-Final Inspection | 10/14/2011 | 10/17/2011 | 10/17/2011 2:16:02 PM | P | FAIL |
|
|
Provide functional testing of the smoke evac system. Provide annual tag for the fire extinguisher and finish installing doors and hardware.
|
BLD11-01890
| FIRE-Final Inspection | 10/17/2011 | 10/17/2011 | 10/17/2011 2:15:16 PM | P | FAIL |
|
|
Provide functional testing of the smoke evac system. Provide fire extinguisher and repair the emergency lighting.
|
FIR11-00515
| INSP-Final Inspection | 10/17/2011 | 10/17/2011 | 10/17/2011 2:14:26 PM | P | PASS |
|
|
permit finaled
|
FIR11-00423
| INSP-Final Inspection | 10/17/2011 | 10/17/2011 | 10/17/2011 2:14:04 PM | P | PASS |
|
|
permit finaled
|
BLD11-01636
| FIRE-Final Inspection | 10/10/2011 | 10/17/2011 | 10/17/2011 1:10:27 PM | A | FAIL |
|
|
Resubmit plans detailing basement use, repair the exit sign that was non-functional and provide automatic flush bolts on the inactive leaf of the main exit.
|
FIR11-00399
| INSP-Final Inspection | 10/17/2011 | 10/17/2011 | 10/17/2011 11:08:23 AM | P | PASS |
|
|
Permit finaled
|
FIR11-00514
| INSP-Final Inspection | 10/17/2011 | 10/17/2011 | 10/17/2011 11:07:24 AM | P | PASS |
|
|
Permit finaled
|
BLD11-02407
| FIRE-Final Inspection | 10/14/2011 | 10/17/2011 | 10/17/2011 10:35:17 AM | A | PASS |
|
|
Life safety passed. Fire extinguisher contractor is on his way to tag and mount the fire extinguisher.
|
BLD11-02292
| FIRE-Final Inspection | 10/14/2011 | 10/17/2011 | 10/17/2011 10:10:47 AM | A | FAIL |
|
|
Provide building address. Provide exit signs as discussed. Provide single action hardware on the west front door as discussed.
|
FIR11-00517
| INSP-Sprinkler Rough-in/Hydro | 10/14/2011 | 10/17/2011 | 10/17/2011 9:16:52 AM | A | PASS |
|
|
Only the IBR has been installed at this time. Piping is ok to cover.
|
BLD11-01844
| FIRE-Final Inspection | 10/13/2011 | 10/17/2011 | 10/17/2011 8:00:41 AM | A | PASS |
|
|
life safety passed
|