ESC12-00403
| General Inspection | 10/17/2012 | 10/17/2012 | 10/17/2012 12:00:00 AM | | FAIL |
|
|
Revised dewatering plan delinquent.
|
ESC12-00403
| Conference | 10/17/2012 | 10/17/2012 | 10/17/2012 12:00:00 AM | A | DONE |
|
|
Discussed with reps from Hoffman, JUMP, ACHD and Strata about the illicit discharges occurring on Sept 6 and again on Sept 14 and the potential illicit discharge occurring week of 10/8. Also discussed the delinquent revised dewatering plan due Sept 28. Hoffman plans to implement an infiltration swale per approved plans to retain all water on site. Hoffman will submit a schedule/plan of action to the ACHD and the City for the construction of the swale no later than the end of the day. City requested sizing calculations for the swale. Hoffman requested permission to continue dewatering to the MS4 until the swale is built. ACHD temporarily granted approval until a plan of action/schedule can be reviewed.
|