FIR13-00526
| INSP-Sprinkler Rough-in | 10/17/2013 | 10/17/2013 | 10/18/2013 4:19:34 PM | P | PART |
|
|
Verified previous correction items are finished. Overhead fire sprinkler work okay to cover.
|
FIR12-00550
| INSP-Final Inspection | 10/16/2013 | 10/17/2013 | 10/18/2013 4:11:48 PM | A | PART |
|
|
Phase three fire sprinkler work completed.
|
FIR13-00252
| INSP-Sprinkler Rough-in | 10/17/2013 | 10/17/2013 | 10/18/2013 6:33:05 AM | P | NR |
|
|
jonathan - verify tenting Phone #: ###-#### *Noted several areas in need of adjustment to provide adequate cold cavity protection.
|
BLD13-02723
| FIRE-Final Inspection | 10/17/2013 | 10/17/2013 | 10/18/2013 6:29:02 AM | P | PASS |
|
|
Scope of rack permit work finished. Storage not to exceed 12' per plan review documents. Discussed occupancy permit and pending fire sprinkler system install.
|
BLD13-01269
| FIRE-Final Inspection | 10/17/2013 | 10/17/2013 | 10/17/2013 2:02:38 PM | P | PASS |
|
|
Noted correction items verified for completion. Fire life safety passed.
|
FIR13-00541
| INSP-Final Inspection | 10/16/2013 | 10/17/2013 | 10/17/2013 2:01:20 PM | P | PASS |
|
|
Fire sprinkler permit work passed final inspection.
|
BLD13-01695
| FIRE-Final Inspection | 10/16/2013 | 10/17/2013 | 10/17/2013 2:00:06 PM | A | PART |
|
|
Per contractor, plan modifications are pending to include a second relocation of starbucks. Remainder of demo work and new work in the pharmacy passed life safety inspection.
|
BLD13-01953
| FIRE-Final Inspection | 10/16/2013 | 10/17/2013 | 10/17/2013 1:55:59 PM | A | PASS |
|
|
Fire life safety inspection completed satisfactory.
|
FIR13-00310
| INSP-Final Inspection | 10/16/2013 | 10/17/2013 | 10/17/2013 1:45:52 PM | A | PASS |
|
|
Fire sprinkler permit work completed and passed final inspection.
|