MEC14-04393
| Final | 10/17/2014 | 10/17/2014 | 10/17/2014 3:19:59 PM | P | FAIL |
|
|
installer brandan ###-#### Phone #: ###-#### >> Inspection requested via web by Dustin Rich Need flue test. Cannot pump condensate into building sewer drain. Need to terminate at approved location. Need to support pvc flue every 4 feet. Line set not installed and a/c
|
MEC14-04393
| Pressure Test | 10/17/2014 | 10/17/2014 | 10/17/2014 3:18:17 PM | P | FAIL |
|
|
p/t is for flue installer brandan ###-#### Phone #: ###-#### >> Inspection requested via web by Dustin Rich need flue test
|
MEC14-03466
| Final | 10/17/2014 | 10/17/2014 | 10/17/2014 3:07:40 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Karl Hestekin
|
MEC14-04484
| Final | 10/17/2014 | 10/17/2014 | 10/17/2014 2:34:18 PM | P | PASS |
|
|
Please be in the early afternoon with call on way Peter or June ###-####. Thanks Phone #: ###-#### >> Inspection requested via web by Allie Courter
|
MEC14-04414
| Pressure Test | 10/16/2014 | 10/17/2014 | 10/17/2014 2:02:51 PM | P | PASS |
|
|
No Heat: Electric to Gas Conversion, need pressure test 1 - 2 PM for meter set, contact Skip (QHC) @ ###-#### or Kevin (QHC) @ Phone #: ###-#### >> Inspection requested via web by Kevin Pratley 20# test from new meter to furnace
|
MEC14-04465
| Final | 10/17/2014 | 10/17/2014 | 10/17/2014 1:52:49 PM | P | PASS |
|
|
Pat// please call before Phone #: ###-####
|
MEC13-05287
| Rough-in | 10/16/2014 | 10/17/2014 | 10/17/2014 11:52:59 AM | A | PASS |
|
|
Re-inspect 5th floor / mech case, Makers Studio. Onsite contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae ok to cover chase at makers studio and ok to insulate ducts at 6th floor.
|