Inspections for the day of: Friday, October 17, 2014.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy James
TitleMEC-COM/RES INSPECTOR
Phone #794-9461
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC14-04393 Final10/17/201410/17/201410/17/2014 3:19:59 PMPFAIL
installer brandan ###-#### Phone #: ###-#### >> Inspection requested via web by Dustin Rich
Need flue test. Cannot pump condensate into building sewer drain. Need to terminate at approved location. Need to support pvc flue every 4 feet. Line set not installed and a/c
MEC14-04393 Pressure Test10/17/201410/17/201410/17/2014 3:18:17 PMPFAIL
p/t is for flue
installer brandan ###-#### Phone #: ###-#### >> Inspection requested via web by Dustin Rich
need flue test
MEC14-03466 Final10/17/201410/17/201410/17/2014 3:07:40 PMPPASS
Phone #: ###-#### >> Inspection requested via web by Karl Hestekin
MEC14-04484 Final10/17/201410/17/201410/17/2014 2:34:18 PMPPASS
Please be in the early afternoon with call on way Peter or June ###-####. Thanks Phone #: ###-#### >> Inspection requested via web by Allie Courter
MEC14-04414 Pressure Test10/16/201410/17/201410/17/2014 2:02:51 PMPPASS
No Heat: Electric to Gas Conversion, need pressure test 1 - 2 PM for meter set, contact Skip (QHC) @ ###-#### or Kevin (QHC) @ Phone #: ###-#### >> Inspection requested via web by Kevin Pratley
20# test from new meter to furnace
MEC14-04465 Final10/17/201410/17/201410/17/2014 1:52:49 PMPPASS
Pat// please call before Phone #: ###-####
MEC13-05287 Rough-in10/16/201410/17/201410/17/2014 11:52:59 AMAPASS
Re-inspect 5th floor / mech case, Makers Studio. Onsite contact: Ben Skelton. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae
ok to cover chase at makers studio and ok to insulate ducts at 6th floor.