FIR16-00623
| INSP-Final Inspection | 10/17/2016 | 10/17/2016 | 10/18/2016 11:11:44 AM | P | FAIL |
|
|
Need annual inspection for the sprinkler system prior to a final sign off.
|
FIR16-00540
| INSP-Sprinkler Rough-in | 10/17/2016 | 10/17/2016 | 10/17/2016 1:10:51 PM | P | PART |
|
|
See the city aproved plans for piping above hardlids that is marked "ok" for cover.
|
FIR16-00636
| INSP-Final Inspection | 10/17/2016 | 10/17/2016 | 10/17/2016 11:13:24 AM | P | PASS |
|
|
Permit finaled
|
FIR16-00453
| INSP-Final Inspection | 10/14/2016 | 10/17/2016 | 10/17/2016 11:13:02 AM | A | FAIL |
|
|
All devices tested and verified except the duct smoke detectors are installed on the supply side of the hvac unit instead of the exhaust side. They will need to be relocated and tested.
|